20543 W OVERLOOK CT 91326
Certificate Information: 20543 W OVERLOOK CT 91326
- Application / Permit
- 23047-20000-00840
- Plan Check / Job No.
- B23VN06767
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- EPLAN NEW 34' X 19' IRREGULAR SHAPED POOL WITH 11' X 8' IRREGULAR SHAPED SPA; PER STANDARD PLAN AND ENGINEERING DETAIL
- Permit Issued
- Issued on 11/7/2023
- Issuing Office
- Current Status
- CofO Issued on 8/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2023 | SELLA BENYAMIN |
| Corrections Issued | 5/30/2023 | SELLA BENYAMIN |
| Quality Review Completed | 6/1/2023 | STEVEN KIM |
| Plan Check Approved | 10/12/2023 | SELLA BENYAMIN |
| Issued | 11/7/2023 | APPLICANT |
| CofO in Progress | 8/13/2024 | JEFFREY PARD |
| Permit Finaled | 8/14/2024 | JOHN JANSON |
| CofO Issued | 8/14/2024 | JOHN JANSON |
| Permit Finaled | 8/14/2024 | JOHN JANSON |
Permit Application Clearance Information
| "T" removal | Cleared | 5/30/2023 | ASHLEY RODARTE |
| Specific Plan | Cleared | 5/30/2023 | STEVEN WECHSLER |
| Tract Map conditions | Cleared | 5/30/2023 | ASHLEY RODARTE |
| ZA Case | Cleared | 5/30/2023 | ASHLEY RODARTE |
| Construction near power lines | Cleared | 8/31/2023 | RIDWAN HARDY |
| Miscellaneous | Cleared | 9/13/2023 | STEVEN WECHSLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 11/13/2023 | Approved | STEVEN BACK |
| Special/Order Compliance | 11/13/2023 | Corrections Issued | STEVEN BACK |
| Deck | 6/17/2024 | Approved | STEVEN BACK |
| Deputy Shotcrete | 6/17/2024 | Corrections Issued | STEVEN BACK |
| Enclosure/Fence | 6/17/2024 | Corrections Issued | STEVEN BACK |
| Grounding or Bonding | 6/17/2024 | Partial Approval | STEVEN BACK |
| Enclosure/Fence | 6/28/2024 | Approved | JEFFREY PARD |
| Equipment Noise Level | 8/6/2024 | Approved | ALFREDO FLORES |
| SGSOV-Seismic Gas S/O Valve | 8/9/2024 | SGSOV Not Ready | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 8/12/2024 | Approved | JEFFREY PARD |
| Final | 8/12/2024 | OK to Issue CofO | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 8/12/2024 | SGSOV Approved | JEFFREY PARD |