131 S VISTA ST 90036

Certificate Information: 131 S VISTA ST 90036

Application / Permit
23047-20000-00813
Plan Check / Job No.
B23VN06473
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 23'-9" X 17'-3" SWIMMING POOL W/ 7'10-1/2" X 7'10-1/2" SPA PER CITY STD PLAN #268 WITH SUPPLEMENTAL POOL COVERR VAULT DETAIL.
Permit Issued
Issued on 10/5/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/17/2023 APPLICANT
Assigned to Plan Check Engineer 5/17/2023 HAYATO TSUCHIYA
Corrections Issued 5/17/2023 HAYATO TSUCHIYA
Issued 10/5/2023 APPLICANT
CofO in Progress 4/26/2024 AMIR NAZARIAN
CofO Issued 5/1/2024 DEROLD HAUFF
Permit Finaled 5/1/2024 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 7/10/2023 DAMIAN GATTO
HPOZ Cleared 7/10/2023 DAMIAN GATTO
Miscellaneous Cleared 7/10/2023 DAMIAN GATTO
Miscellaneous Cleared 7/10/2023 DAMIAN GATTO
ZI Cleared 7/10/2023 DAMIAN GATTO
Construction near power lines Cleared 10/2/2023 RIDWAN HARDY

Contact Information

Contractor Emerge Pools Inc; Lic. No.: 1010243-C53 14740 VINCENNES STREET      PANORAMA CITY, CA 91402
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 10/24/2023 Approved LILIANA PORTILLO
Deputy Shotcrete 10/27/2023 Conditional Approval BRENDAN MORELLI
Gas Piping or Gas Test 11/3/2023 Approved LILIANA PORTILLO
Pool Piping 11/3/2023 Approved LILIANA PORTILLO
Enclosure/Fence 1/17/2024 Corrections Issued LILIANA PORTILLO
Grounding or Bonding 1/17/2024 Approved LILIANA PORTILLO
Enclosure/Fence 1/26/2024 Corrections Issued LILIANA PORTILLO
Enclosure/Fence 1/30/2024 Approved LILIANA PORTILLO
Pool Equipment Noise Test 3/7/2024 Approved ANDEY CHAPARRO
Excavation/Setback/Form/Re-Bar 3/11/2024 Corrections Issued AMIR NAZARIAN
Final 3/11/2024 Corrections Issued AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 3/11/2024 SGSOV Not Ready AMIR NAZARIAN
Excavation/Setback/Form/Re-Bar 4/4/2024 Approved AMIR NAZARIAN
Final 4/4/2024 Conditional Approval AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 4/4/2024 SGSOV Approved AMIR NAZARIAN
Final 4/26/2024 OK to Issue CofO AMIR NAZARIAN