12014 W HARTSOOK ST 91607
Certificate Information: 12014 W HARTSOOK ST 91607
- Application / Permit
- 23047-20000-00800
- Plan Check / Job No.
- B23VN06364
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 14' X 30' POOL WITH 7' X 7' SPA PER STANDARD PLAN 270
- Permit Issued
- Issued on 5/25/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 5/16/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 5/25/2023 | ALEC MOUSAKHANIAN |
| Issued | 5/25/2023 | APPLICANT |
| CofO in Progress | 4/22/2024 | CHRISTOPHER ROJAS |
| Permit Finaled | 5/8/2024 | RUBEN SALAS |
| CofO Issued | 5/8/2024 | RUBEN SALAS |
| Permit Finaled | 5/8/2024 | RUBEN SALAS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Green Paradise Creation Inc; Lic. No.: 1017683-C53 | 17933 TOPHAM ST ENCINO, CA 91316 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 6/5/2023 | Approved | JACK KARGODORIAN |
| Deputy Shotcrete | 6/7/2023 | Partial Approval | JACK KARGODORIAN |
| Rough-Electrical | 10/16/2023 | Approved | JOHN COLEMAN |
| Rough-Plumbing | 10/16/2023 | Approved | JOHN COLEMAN |
| Gas Piping or Gas Test | 11/3/2023 | No Access for Inspection | JOHN COLEMAN |
| Enclosure/Fence | 2/26/2024 | Corrections Issued | KIRK SANDERS |
| Enclosure/Fence | 2/28/2024 | Corrections Issued | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 3/22/2024 | Approved | KIRK SANDERS |
| Final | 3/22/2024 | Corrections Issued | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 3/22/2024 | SGSOV Not Ready | KIRK SANDERS |
| Equipment Noise Level | 3/26/2024 | Approved | FELIPE PENICHE |
| Pool Equipment Noise Test | 3/26/2024 | Approved | FELIPE PENICHE |
| Final | 4/1/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 4/1/2024 | SGSOV Approved | CHRISTOPHER ROJAS |