20344 W WILLOUGHBY LANE 91326
Certificate Information: 20344 W WILLOUGHBY LANE 91326
- Application / Permit
- 23047-20000-00775
- Plan Check / Job No.
- B23VN06077
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (n) irregular shape 31'x37' pool and 9'x9' spa per la standard plan #268 and supplemental details. shotcrete. gas heater. 1 of 2
- Permit Issued
- Issued on 5/25/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/15/2023 | JESSE ARELLANO |
| Corrections Issued | 5/16/2023 | JESSE ARELLANO |
| Building Plans Picked Up | 5/18/2023 | APPLICANT |
| Issued | 5/25/2023 | APPLICANT |
| CofO in Progress | 9/19/2023 | JEFFREY PARD |
| Permit Finaled | 10/12/2023 | JOHN JANSON |
| CofO Issued | 10/12/2023 | JOHN JANSON |
| Permit Finaled | 10/12/2023 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/16/2023 | JESSE ARELLANO |
| "T" removal | Cleared | 5/23/2023 | ASHLEY RODARTE |
Contact Information
| Contractor | Aiden Pools; Lic. No.: 1053685-C53 | 1276 E COLORADO BLVD_SUITE 210 PASADENA, CA 91106 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Enclosure/Fence | 6/7/2023 | Corrections Issued | STEVEN BACK |
| Pre-Gunite | 6/7/2023 | Approved | STEVEN BACK |
| Deputy Shotcrete | 6/8/2023 | Approved | JEFFREY PARD |
| Deck | 6/13/2023 | Approved | JEFFREY PARD |
| Enclosure/Fence | 8/22/2023 | Approved | JEFFREY PARD |
| Equipment Noise Level | 9/8/2023 | Approved | ALFREDO FLORES |
| Pool Equipment Noise Test | 9/8/2023 | Approved | ALFREDO FLORES |
| Excavation/Setback/Form/Re-Bar | 9/13/2023 | Approved | JEFFREY PARD |
| Final | 9/13/2023 | Corrections Issued | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 9/13/2023 | SGSOV Approved | JEFFREY PARD |
| Final | 9/18/2023 | OK to Issue CofO | JEFFREY PARD |