2915 N LAKERIDGE DR 90068

Certificate Information: 2915 N LAKERIDGE DR 90068

Application / Permit
23047-20000-00760
Plan Check / Job No.
B23VN05937
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW (32'-0"x20'-9"), POOL AND (8'-8"x7'-3") SPA ON PILES PER ENGINEERING DESIGN
Permit Issued
Issued on 2/13/2025
Issuing Office
Valley
Current Status
CofO Issued on 10/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/8/2023 APPLICANT
Assigned to Plan Check Engineer 5/11/2023 PETER MOSESIAN
Corrections Issued 5/14/2023 PETER MOSESIAN
Quality Review Completed 5/16/2023 OMID HEDAYAT
Building Plans Picked Up 6/13/2023 APPLICANT
Plan Check Approved 8/1/2023 PETER MOSESIAN
Issued 2/13/2025 APPLICANT
CofO in Progress 10/3/2025 BRIAN SULLIVAN
Permit Finaled 10/4/2025 DEROLD HAUFF
CofO Issued 10/4/2025 DEROLD HAUFF
Permit Finaled 10/4/2025 DEROLD HAUFF

Permit Application Clearance Information

Specific Plan Cleared 6/29/2023 NATHAN ROMINE
ZI Cleared 6/29/2023 NATHAN ROMINE
Grading Pre-Inspection Cleared 7/26/2023 PETER MOSESIAN

Contact Information

Architect Salcedo,, Glen Charles; Lic. No.: C33143 P O BOX 14202      VAN NUYS, CA 91409
Contractor Owner-Builder       ,
Engineer Irby,, Michael Carey; Lic. No.: C33143 PO BOX 385      MIDDLETON, ID 83644
Engineer Mirzadeh,, Amir; Lic. No.: C58119 P O BOX 572110      TARZANA, CA 91357
Engineer Moeini,, Soheil; Lic. No.: C84000 11022 SANTA MONICA BLVD STE 440      LOS ANGELES, CA 90025
Geologist Rahimikian,, Pedram; Lic. No.: EG2683 21414 ARCOS DRIVE      WOODLAND HILLS, CA 91364

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 4/2/2025 Corrections Issued BRIAN SULLIVAN
Deputy Other (see comments) 4/3/2025 Conditional Approval BRENDAN MORELLI
Deputy Other (see comments) 4/7/2025 Conditional Approval BRIAN SULLIVAN
Deputy Other (see comments) 4/10/2025 Conditional Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 4/14/2025 Partial Approval BRIAN SULLIVAN
Deputy Shotcrete 5/5/2025 Conditional Approval BRIAN SULLIVAN
Pre-Gunite 5/5/2025 Approved BRIAN SULLIVAN
Deputy Shotcrete 5/8/2025 Conditional Approval BRIAN SULLIVAN
Deck 7/1/2025 Partial Approval BRIAN SULLIVAN
Enclosure/Fence 8/19/2025 Corrections Issued BRIAN SULLIVAN
Enclosure/Fence 8/29/2025 Conditional Approval BRIAN SULLIVAN
Equipment Noise Level 10/2/2025 Approved JUAN ESCOTO DELGADO
Excavation/Setback/Form/Re-Bar 10/2/2025 Approved BRIAN SULLIVAN
Final 10/2/2025 OK to Issue CofO BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 10/2/2025 SGSOV Approved BRIAN SULLIVAN