7938 S KENYON AVE 90045
Certificate Information: 7938 S KENYON AVE 90045
- Application / Permit
- 23047-20000-00708
- Plan Check / Job No.
- B23VN05549
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 14'-0" x 28'-0" POOL AND 6'-0" x 6'-0" SPA PER LA CITY STD PLAN No. 268.
- Permit Issued
- Issued on 10/25/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/1/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 5/1/2023 | LUISANGEL VALENZUELA |
| Issued | 10/25/2023 | APPLICANT |
| CofO in Progress | 3/8/2024 | TEMISTOCLES CAAL |
| Permit Finaled | 3/9/2024 | DANIEL ORRANTE |
| CofO Issued | 3/9/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/9/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/1/2023 | LUISANGEL VALENZUELA |
| Construction near power lines | Cleared | 8/11/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/11/2023 | RIDWAN HARDY |
Contact Information
| Contractor | E H D Builders Inc; Lic. No.: 1034101-B | 18375 VENTURA BLVD 122 TARZANA, CA 91356 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/9/2023 | Approved | BOBBY KEY |
| Grounding or Bonding | 11/9/2023 | Partial Approval | BOBBY KEY |
| Pool Piping | 11/9/2023 | Partial Approval | BOBBY KEY |
| Pre-Gunite | 11/9/2023 | Approved | BOBBY KEY |
| Deputy Shotcrete | 11/13/2023 | Conditional Approval | BOBBY KEY |
| Gas Piping or Gas Test | 11/27/2023 | Approved | BOBBY KEY |
| Rough-Electrical | 11/27/2023 | Approved | BOBBY KEY |
| Rough-Plumbing | 11/27/2023 | Approved | BOBBY KEY |
| Deck | 1/10/2024 | Approved | BOBBY KEY |
| Grounding or Bonding | 1/10/2024 | Approved | BOBBY KEY |
| Special/Order Compliance | 1/10/2024 | Partial Inspection | BEN MOLSTAD |
| Enclosure/Fence | 2/9/2024 | Not Ready for Inspection | BOBBY KEY |
| Enclosure/Fence | 2/12/2024 | Corrections Issued | HERBERT GIRON |
| Enclosure/Fence | 2/15/2024 | Approved | BOBBY KEY |
| Pool Equipment Noise Test | 2/27/2024 | Approved | JAMES VORHIS |
| ELECTRICAL-Final | 3/5/2024 | Approved | BOBBY KEY |
| Final | 3/5/2024 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 3/5/2024 | SGSOV Approved | BOBBY KEY |
| ELECTRICAL-Final | 3/7/2024 | Approved | TEMISTOCLES CAAL |
| Final | 3/7/2024 | OK to Issue CofO | TEMISTOCLES CAAL |
| PLUMBING-Final | 3/7/2024 | Approved | TEMISTOCLES CAAL |