10408 N WISH AVE 91344
Certificate Information: 10408 N WISH AVE 91344
- Application / Permit
- 23047-20000-00590
- Plan Check / Job No.
- B23VN04402
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 19'-0" x 30'-0" IRREGULAR SHAPED POOL WITH 7'-0" x 7'-0" SPA PER LA CITY STANDARD PLAN # 268.
- Permit Issued
- Issued on 7/12/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/6/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 4/6/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 7/12/2023 | SARKIS HARABEDIAN |
| Issued | 7/12/2023 | APPLICANT |
| CofO in Progress | 9/29/2023 | JAVIER RAMOS JR |
| Permit Finaled | 11/14/2023 | RUBEN SALAS |
| CofO Issued | 11/14/2023 | RUBEN SALAS |
| Permit Finaled | 11/14/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/7/2023 | WALTER RAMIREZ |
Contact Information
| Contractor | Sparkling Touch Pool; Lic. No.: 1021177-C53 | 10027 MCBROOM ST SUNLAND, CA 91040 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 7/27/2023 | Approved | JAVIER RAMOS JR |
| Deputy Shotcrete | 8/4/2023 | Conditional Approval | JAVIER RAMOS JR |
| Grounding or Bonding | 8/9/2023 | Approved | JAVIER RAMOS JR |
| Enclosure/Fence | 8/18/2023 | Corrections Issued | JAVIER RAMOS JR |
| Equipment Noise Level | 8/29/2023 | Approved | FELIPE PENICHE |
| Pool Equipment Noise Test | 8/29/2023 | Approved | FELIPE PENICHE |
| Excavation/Setback/Form/Re-Bar | 8/30/2023 | Approved | MISAEL ESPARZA |
| Final | 8/30/2023 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 8/30/2023 | SGSOV Not Ready | MISAEL ESPARZA |
| Enclosure/Fence | 9/20/2023 | Approved | JAVIER RAMOS JR |
| Final | 9/20/2023 | OK to Issue CofO | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 9/20/2023 | SGSOV Approved | JAVIER RAMOS JR |