11016 N LINDLEY AVE 91344

Certificate Information: 11016 N LINDLEY AVE 91344

Application / Permit
23047-20000-00565
Plan Check / Job No.
B23VN04109
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
ePlan NEW 22'-10" X 30'-4" POOL AND '8 X '8 SPA W/ BAJA PER LA CITY STD PLAN No. 265
Permit Issued
Issued on 4/25/2023
Issuing Office
Current Status
CofO Issued on 11/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2023 APPLICANT
Assigned to Plan Check Engineer 4/3/2023 LUISANGEL VALENZUELA
Corrections Issued 4/4/2023 LUISANGEL VALENZUELA
Applicant returned to address corrections 4/19/2023 LUISANGEL VALENZUELA
Plan Check Approved 4/24/2023 LUISANGEL VALENZUELA
Issued 4/25/2023 APPLICANT
CofO in Progress 11/17/2023 DAVID SCANTLIN
Permit Finaled 11/27/2023 JOHN JANSON
CofO Issued 11/27/2023 JOHN JANSON
Permit Finaled 11/27/2023 JOHN JANSON

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/15/2023 Corrections Issued DAVID SCANTLIN
Final 5/15/2023 Corrections Issued DAVID SCANTLIN
Gas Piping or Gas Test 5/15/2023 Approved DAVID SCANTLIN
Rough-Electrical 5/15/2023 Approved DAVID SCANTLIN
Rough-Plumbing 5/15/2023 Approved DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 5/18/2023 Approved DAVID SCANTLIN
Rough-Plumbing 5/18/2023 Approved DAVID SCANTLIN
Deck 6/12/2023 Approved STEVEN BACK
Pre-Gunite 6/12/2023 Approved STEVEN BACK
Enclosure/Fence 10/23/2023 Corrections Issued JEFFREY PARD
Enclosure/Fence 10/25/2023 Not Ready for Inspection DAVID SCANTLIN
Enclosure/Fence 10/31/2023 Corrections Issued STEVEN BACK
Enclosure/Fence 11/3/2023 Approved STEVEN BACK
Equipment Noise Level 11/8/2023 Approved ALFREDO FLORES
ELECTRICAL-Final 11/15/2023 Approved DAVID SCANTLIN
Final 11/15/2023 OK to Issue CofO DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 11/15/2023 SGSOV Approved DAVID SCANTLIN