24310 W CALVERT ST 91367
Certificate Information: 24310 W CALVERT ST 91367
- Application / Permit
- 23047-20000-00540
- Plan Check / Job No.
- B23VN04027
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- Eplan; New (30'-0" x 14'-0") pool and spa
- Permit Issued
- Issued on 5/18/2023
- Issuing Office
- Current Status
- CofO Issued on 8/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2023 | MOHAMMAD ESMAILI |
| Corrections Issued | 4/4/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 4/19/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 5/11/2023 | MOHAMMAD ESMAILI |
| No Progress | 5/17/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 5/17/2023 | MOHAMMAD ESMAILI |
| Issued | 5/18/2023 | APPLICANT |
| CofO in Progress | 8/16/2023 | TROY SANDERS |
| Permit Finaled | 8/23/2023 | JOHN JANSON |
| CofO Issued | 8/23/2023 | JOHN JANSON |
| Permit Finaled | 8/23/2023 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/11/2023 | MOHAMMAD ESMAILI |
Contact Information
| Contractor | Intex Design And Construction Inc; Lic. No.: 981718-C53 | 15021 VENTURA BLVD STE 520 SHERMAN OAKS, CA 91403 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/15/2023 | Approved | PETER FOLLING |
| Gas Piping or Gas Test | 6/15/2023 | Approved | PETER FOLLING |
| Grounding or Bonding | 6/15/2023 | Not Ready for Inspection | PETER FOLLING |
| Pool Piping | 6/15/2023 | Approved | PETER FOLLING |
| Pre-Gunite | 6/15/2023 | Approved | PETER FOLLING |
| Rough-Electrical | 6/15/2023 | Approved | PETER FOLLING |
| Deputy Shotcrete | 6/16/2023 | Approved | HORACE FULTZ |
| Deputy Shotcrete | 6/16/2023 | Conditional Approval | JUSTIN HAWLEY |
| Enclosure/Fence | 7/28/2023 | Corrections Issued | MORRIS JACKSON |
| Grounding or Bonding | 7/28/2023 | Approved | MORRIS JACKSON |
| Enclosure/Fence | 8/1/2023 | Approved | TROY SANDERS |
| Special/Order Compliance | 8/1/2023 | Approved | TROY SANDERS |
| Pool Equipment Noise Test | 8/8/2023 | Approved | ALFREDO FLORES |
| Final | 8/9/2023 | OK to Issue CofO | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 8/9/2023 | SGSOV Approved | TROY SANDERS |