12262 W RICHWOOD DR 90049

Certificate Information: 12262 W RICHWOOD DR 90049

Application / Permit
23047-20000-00491
Plan Check / Job No.
B23VN03769
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 18'-1" x 40' SWIMMING POOL (W/ 4'-0 1/4" x 40' CATCH POOL) ON PILES; ALL WORK PER ENGINEERING DESIGN
Permit Issued
Issued on 1/3/2024
Issuing Office
Current Status
Issued on 1/3/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/24/2023 APPLICANT
Assigned to Plan Check Engineer 3/30/2023 SEAN SHAHMIRI
Corrections Issued 4/3/2023 SEAN SHAHMIRI
Quality Review Completed 4/4/2023 OMID HEDAYAT
Building Plans Picked Up 4/5/2023 APPLICANT
Applicant returned to address corrections 4/17/2023 SEAN SHAHMIRI
Applicant returned to address corrections 5/1/2023 SEAN SHAHMIRI
Applicant returned to address corrections 5/8/2023 SEAN SHAHMIRI
Applicant returned to address corrections 6/15/2023 SEAN SHAHMIRI
Applicant returned to address corrections 6/20/2023 SEAN SHAHMIRI
Applicant returned to address corrections 1/3/2024 SEAN SHAHMIRI
Plan Check Approved 1/3/2024 SEAN SHAHMIRI
Issued 1/3/2024 APPLICANT

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Other (see comments) 4/3/2024 Conditional Approval MICHAEL PELHAM
Piling/Pier/Caisson 4/16/2024 Partial Approval CARLOS MATAMOROS
Deputy Other (see comments) 4/19/2024 Conditional Approval CARLOS MATAMOROS
Deputy Other (see comments) 5/8/2024 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 5/9/2024 Partial Approval CARLOS MATAMOROS
Deputy Shotcrete 6/7/2024 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 6/7/2024 Partial Approval KEVIN SARGSYAN
Deputy Other (see comments) 8/22/2025 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 8/22/2025 Corrections Issued CARLOS MATAMOROS