3418 W LARGA AVE 90039

Certificate Information: 3418 W LARGA AVE 90039

Application / Permit
23047-20000-00414
Plan Check / Job No.
B23VN03326
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 12'-0" X 26'-9" POOL WITH 5'-6" X 5'-6" SPA PER STANDARD PLAN 268 AND ENGINEER DETAIL
Permit Issued
Issued on 6/28/2024
Issuing Office
Metro
Current Status
CofO Issued on 7/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2023 APPLICANT
Assigned to Plan Check Engineer 3/20/2023 HAYATO TSUCHIYA
Corrections Issued 3/22/2023 HAYATO TSUCHIYA
Building Plans Picked Up 3/29/2023 APPLICANT
Applicant returned to address corrections 6/5/2024 DANIEL ABRAMYAN
Plan Check Approved 6/27/2024 ALEC MOUSAKHANIAN
Issued 6/28/2024 APPLICANT
CofO in Progress 7/8/2026 NICHOLAS LOPEZ
CofO Issued 7/9/2026 DEROLD HAUFF
Permit Finaled 7/9/2026 DEROLD HAUFF

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 8/21/2024 Approved THOMAS LOGRASSO
Deputy Shotcrete 8/23/2024 Conditional Approval THOMAS LOGRASSO
Deck 8/18/2025 Approved NICHOLAS LOPEZ
Enclosure/Fence 4/20/2026 Not Ready for Inspection NICHOLAS LOPEZ
Enclosure/Fence 4/21/2026 Corrections Issued ALIZAH MAYAGOITIA
Enclosure/Fence 4/22/2026 Approved NICHOLAS LOPEZ
Pool/Spa Cover 4/24/2026 Corrections Issued NICHOLAS LOPEZ
Pool Equipment Noise Test 6/18/2026 Approved JONATHAN FRANCHINI
Excavation/Setback/Form/Re-Bar 6/22/2026 Approved NICHOLAS LOPEZ
Final 6/22/2026 Corrections Issued NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 6/22/2026 SGSOV Not Ready NICHOLAS LOPEZ
Pre-Inspection 6/24/2026 Partial Inspection NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 6/24/2026 SGSOV Not Ready NICHOLAS LOPEZ
Final 7/8/2026 OK to Issue CofO NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 7/8/2026 SGSOV Approved NICHOLAS LOPEZ