250 S BRISTOL AVE 90049
Certificate Information: 250 S BRISTOL AVE 90049
- Application / Permit
- 23047-20000-00398
- Plan Check / Job No.
- B23VN03123
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ADD A (N) 8' X 8' SPA TO THE (E) POOL - NOT WITHIN THE (E) POOL SHELL PER LA CITY STANDARD PLAN #270.
- Permit Issued
- Issued on 3/13/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2023 | MADISON ODELL |
| Issued | 3/13/2023 | APPLICANT |
| CofO in Progress | 9/20/2023 | OGANES TARAKHCHYAN |
| Permit Finaled | 9/27/2023 | DANIEL ORRANTE |
| CofO Issued | 9/27/2023 | DANIEL ORRANTE |
| Permit Finaled | 9/27/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/13/2023 | MADISON ODELL |
| ZA Case | Cleared | 3/13/2023 | NELSON RODRIGUEZ |
Contact Information
| Contractor | Raub Doug Design & Development Inc; Lic. No.: 723625-B | 14066 ROBLAR ROAD SHERMAN OAKS, CA 91423 |
| Engineer | Cristescu,, Barbu Dan; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Other (see comments) | 5/11/2023 | Conditional Approval | DANIEL ORRANTE |
| Deputy Other (see comments) | 5/12/2023 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 5/23/2023 | Approved | JESUS RODRIGUEZ |
| Enclosure/Fence | 8/8/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Enclosure/Fence | 8/9/2023 | Approved | OGANES TARAKHCHYAN |
| Pool Equipment Noise Test | 9/5/2023 | Approved | JAMES VORHIS |
| Final | 9/13/2023 | Corrections Issued | KEVIN SARGSYAN |
| Pre-Gunite | 9/13/2023 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 9/13/2023 | SGSOV Approved | KEVIN SARGSYAN |
| Final | 9/19/2023 | OK to Issue CofO | OGANES TARAKHCHYAN |