13645 N NORRIS AVE 91342
Certificate Information: 13645 N NORRIS AVE 91342
- Application / Permit
- 23047-20000-00358
- Plan Check / Job No.
- B23VN02768
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ePlan: New 33'-11.5" x 23'-4.75" Swimming Pool with Spa Diameter 9', Baja Step and Slide per Standard Plan #268 and Engineering Details.
- Permit Issued
- Issued on 3/23/2023
- Issuing Office
- Current Status
- CofO Issued on 5/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/9/2023 | DAVID CASTILLO |
| Corrections Issued | 3/10/2023 | DAVID CASTILLO |
| Plan Check Approved | 3/22/2023 | ALFREDO JARA |
| Issued | 3/23/2023 | APPLICANT |
| CofO in Progress | 5/23/2023 | ARAM AVEDISIAN |
| Permit Finaled | 5/25/2023 | MICHAEL SMITH |
| CofO Issued | 5/25/2023 | MICHAEL SMITH |
| Permit Finaled | 5/25/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/22/2023 | DAVID CASTILLO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: NA86051 | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/7/2023 | Approved | ARAM AVEDISIAN |
| Gas Piping or Gas Test | 4/7/2023 | Approved | ARAM AVEDISIAN |
| Grounding or Bonding | 4/7/2023 | Partial Approval | ARAM AVEDISIAN |
| Pool Piping | 4/7/2023 | Approved | ARAM AVEDISIAN |
| Pre-Gunite | 4/7/2023 | Approved | ARAM AVEDISIAN |
| Rough-Electrical | 4/7/2023 | Approved | ARAM AVEDISIAN |
| Grounding or Bonding | 4/17/2023 | Approved | ARAM AVEDISIAN |
| Enclosure/Fence | 5/2/2023 | Approved | ARAM AVEDISIAN |
| Final | 5/15/2023 | Corrections Issued | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 5/15/2023 | SGSOV Approved | ARAM AVEDISIAN |
| Pool Equipment Noise Test | 5/18/2023 | Approved | FELIPE PENICHE |
| ELECTRICAL-Final | 5/23/2023 | Approved | ARAM AVEDISIAN |
| Final | 5/23/2023 | OK to Issue CofO | ARAM AVEDISIAN |