1078 N MAYBROOK DR 90210
Certificate Information: 1078 N MAYBROOK DR 90210
- Application / Permit
- 23047-20000-00354
- Plan Check / Job No.
- B23VN02743
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 13'-0" x 32'-0" POOL AND 7'-0" x 7'-0" SPA PER LA CITY STANDARD PLAN # 268.
- Permit Issued
- Issued on 3/20/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2023 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 3/3/2023 | MIROOSH KHACHATOORIAN |
| Issued | 3/20/2023 | APPLICANT |
| CofO in Progress | 11/16/2023 | STEPHANIE SWANSON |
| Permit Finaled | 11/18/2023 | DANIEL ORRANTE |
| CofO Issued | 11/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 11/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/3/2023 | MIROOSH KHACHATOORIAN |
| ZA Case | Cleared | 3/17/2023 | MIGUEL GAMBOA |
Contact Information
| Contractor | Noga Pool And Spa Inc; Lic. No.: 946647-C53 | 5739 KANAN ROAD #639 AGOURA HILLS, CA 91301 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/11/2023 | Partial Approval | CHRISTOPHER WILSON |
| Grounding or Bonding | 4/11/2023 | Partial Approval | CHRISTOPHER WILSON |
| Pool Piping | 4/11/2023 | Approved | CHRISTOPHER WILSON |
| Pre-Gunite | 4/11/2023 | Approved | CHRISTOPHER WILSON |
| Rough-Electrical | 4/11/2023 | Partial Approval | CHRISTOPHER WILSON |
| Rough-Plumbing | 4/11/2023 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Shotcrete | 4/12/2023 | Conditional Approval | MICHAEL PELHAM |
| Grounding or Bonding | 5/3/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Enclosure/Fence | 10/4/2023 | Corrections Issued | BRENDAN LOONEY |
| Enclosure/Fence | 10/26/2023 | Corrections Issued | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 11/8/2023 | Approved | BRENDAN LOONEY |
| Final | 11/8/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 11/8/2023 | SGSOV Approved | BRENDAN LOONEY |
| Equipment Noise Level | 11/16/2023 | Approved | ANDEY CHAPARRO |
| Final | 11/16/2023 | OK to Issue CofO | STEPHANIE SWANSON |