558 N BRISTOL AVE 90049

Certificate Information: 558 N BRISTOL AVE 90049

Application / Permit
23047-20000-00348
Plan Check / Job No.
B23VN02722
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW SWIMMING POOL AND SPA PER STANDARD PLAN # 268 AND ENGINEER DETAIL #501
Permit Issued
Issued on 9/12/2023
Issuing Office
Current Status
CofO Issued on 9/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2023 APPLICANT
Assigned to Plan Check Engineer 3/8/2023 JEROME MAGAT PALMA
Corrections Issued 3/11/2023 JEROME MAGAT PALMA
Building Plans Picked Up 3/15/2023 APPLICANT
Quality Review Completed 9/12/2023 FELIX FIGUEROA
Plan Check Approved 9/12/2023 SERGIO MUNIZ
Issued 9/12/2023 APPLICANT
CofO in Progress 9/5/2025 KEVIN SARGSYAN
Permit Finaled 9/11/2025 RICHARD STEINBACH
CofO Issued 9/11/2025 RICHARD STEINBACH
Permit Finaled 9/11/2025 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/10/2023 JEROME MAGAT PALMA
Eng Process Fee Ord 176,300 Cleared 5/1/2023 JASON NG
ZA Case Cleared 5/1/2023 DANG NGUYEN
Construction near power lines Cleared 8/10/2023 RIDWAN HARDY
Construction within easement Cleared 8/10/2023 RIDWAN HARDY
Work Adjacent to Public Way Cleared 8/30/2023 LIAM ODONOVAN

Contact Information

Contractor Walker Pools Incorporated; Lic. No.: 300051-C53 144 W LOS ANGELES AVE #106-178      MOORPARK, CA 93021
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/24/2023 Approved ARAM AVEDISIAN
Grounding or Bonding 10/24/2023 Partial Approval ARAM AVEDISIAN
Pool Piping 10/24/2023 Approved ARAM AVEDISIAN
Pre-Gunite 10/24/2023 Approved ARAM AVEDISIAN
Deputy Shotcrete 10/26/2023 Approved ARAM AVEDISIAN
Gas Piping or Gas Test 5/24/2024 Approved KEVIN SARGSYAN
Pool Piping 5/24/2024 Approved KEVIN SARGSYAN
Rough-Electrical 5/24/2024 Approved KEVIN SARGSYAN
Enclosure/Fence 3/17/2025 Corrections Issued KEVIN SARGSYAN
Enclosure/Fence 4/2/2025 Corrections Issued KEVIN SARGSYAN
Equipment Noise Level 7/17/2025 Approved JAMES VORHIS
Final 8/20/2025 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 8/20/2025 SGSOV Approved KEVIN SARGSYAN
Final 9/5/2025 OK to Issue CofO KEVIN SARGSYAN