428 N CARMELINA AVE 90049
Certificate Information: 428 N CARMELINA AVE 90049
- Application / Permit
- 23047-20000-00324
- Plan Check / Job No.
- B23VN02497
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW IRREG SHAPED SWIMMING POOL AND SPA PER STANDARD PLAN #268 AND ENGINEER DETAIL 501, 554, 630. SEE COMMENTS.
- Permit Issued
- Issued on 4/18/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 3/4/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 3/8/2023 | APPLICANT |
| Applicant returned to address corrections | 3/23/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 4/18/2023 | SERGIO MUNIZ |
| Issued | 4/18/2023 | APPLICANT |
| CofO in Progress | 2/2/2024 | DANIEL ORRANTE |
| CofO in Progress | 2/2/2024 | DANIEL ORRANTE |
| CofO in Progress | 2/3/2024 | KEVIN SARGSYAN |
| Permit Finaled | 2/6/2024 | DANIEL ORRANTE |
| CofO Issued | 2/6/2024 | DANIEL ORRANTE |
| Permit Finaled | 2/6/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/4/2023 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Agam Pool And Spa Inc; Lic. No.: 993464-C53 | 12940 ADDISON STREET SHERMAN OAKS, CA 91423 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Geologist | Feffer,, Joshua R; Lic. No.: EG2138 | 12253 GORHAM AVE LOS ANGELES, CA 90049 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 6/23/2023 | Partial Approval | EVAN COOPER |
| Deputy Other (see comments) | 6/26/2023 | Conditional Approval | EVAN COOPER |
| Deputy Other (see comments) | 6/27/2023 | Conditional Approval | EVAN COOPER |
| Pre-Gunite | 7/20/2023 | Corrections Issued | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 7/21/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Rough-Plumbing | 7/21/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Pre-Gunite | 7/25/2023 | Approved | KEVIN SARGSYAN |
| Deputy Shotcrete | 7/26/2023 | No Access for Inspection | KENNETH NAGLE |
| Deck | 11/13/2023 | Approved | BRENDAN LOONEY |
| Grounding or Bonding | 11/13/2023 | Approved | BRENDAN LOONEY |
| Enclosure/Fence | 11/22/2023 | Approved | CARLOS MATAMOROS |
| Pool Equipment Noise Test | 1/11/2024 | Approved | CLAUDIO MORENO |
| Excavation/Setback/Form/Re-Bar | 1/18/2024 | Approved | KEVIN SARGSYAN |
| Final | 1/18/2024 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 1/18/2024 | SGSOV Approved | KEVIN SARGSYAN |
| Final | 1/23/2024 | OK to Issue CofO | KENNETH NAGLE |
| Final | 2/2/2024 | OK to Issue CofO | KEVIN SARGSYAN |