428 N CARMELINA AVE 90049

Certificate Information: 428 N CARMELINA AVE 90049

Application / Permit
23047-20000-00324
Plan Check / Job No.
B23VN02497
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW IRREG SHAPED SWIMMING POOL AND SPA PER STANDARD PLAN #268 AND ENGINEER DETAIL 501, 554, 630. SEE COMMENTS.
Permit Issued
Issued on 4/18/2023
Issuing Office
Valley
Current Status
CofO Issued on 2/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/28/2023 APPLICANT
Assigned to Plan Check Engineer 3/3/2023 JEROME MAGAT PALMA
Corrections Issued 3/4/2023 JEROME MAGAT PALMA
Building Plans Picked Up 3/8/2023 APPLICANT
Applicant returned to address corrections 3/23/2023 ALEC MOUSAKHANIAN
Plan Check Approved 4/18/2023 SERGIO MUNIZ
Issued 4/18/2023 APPLICANT
CofO in Progress 2/2/2024 DANIEL ORRANTE
CofO in Progress 2/2/2024 DANIEL ORRANTE
CofO in Progress 2/3/2024 KEVIN SARGSYAN
Permit Finaled 2/6/2024 DANIEL ORRANTE
CofO Issued 2/6/2024 DANIEL ORRANTE
Permit Finaled 2/6/2024 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/4/2023 JEROME MAGAT PALMA

Contact Information

Contractor Agam Pool And Spa Inc; Lic. No.: 993464-C53 12940 ADDISON STREET      SHERMAN OAKS, CA 91423
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Geologist Feffer,, Joshua R; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 6/23/2023 Partial Approval EVAN COOPER
Deputy Other (see comments) 6/26/2023 Conditional Approval EVAN COOPER
Deputy Other (see comments) 6/27/2023 Conditional Approval EVAN COOPER
Pre-Gunite 7/20/2023 Corrections Issued KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 7/21/2023 Not Ready for Inspection KEVIN SARGSYAN
Rough-Plumbing 7/21/2023 Not Ready for Inspection KEVIN SARGSYAN
Pre-Gunite 7/25/2023 Approved KEVIN SARGSYAN
Deputy Shotcrete 7/26/2023 No Access for Inspection KENNETH NAGLE
Deck 11/13/2023 Approved BRENDAN LOONEY
Grounding or Bonding 11/13/2023 Approved BRENDAN LOONEY
Enclosure/Fence 11/22/2023 Approved CARLOS MATAMOROS
Pool Equipment Noise Test 1/11/2024 Approved CLAUDIO MORENO
Excavation/Setback/Form/Re-Bar 1/18/2024 Approved KEVIN SARGSYAN
Final 1/18/2024 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 1/18/2024 SGSOV Approved KEVIN SARGSYAN
Final 1/23/2024 OK to Issue CofO KENNETH NAGLE
Final 2/2/2024 OK to Issue CofO KEVIN SARGSYAN