5657 N ST CLAIR AVE 91607

Certificate Information: 5657 N ST CLAIR AVE 91607

Application / Permit
23047-20000-00283
Plan Check / Job No.
B23VN02232
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
eplan New 30'6" X 18' Pool with (2) Baja Steps, New 8'6" X 6' Spa with New Equipment per LA Standard Plan #268 *SEE comment*
Permit Issued
Issued on 11/9/2023
Issuing Office
Current Status
CofO Issued on 12/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/23/2023 APPLICANT
Assigned to Plan Check Engineer 2/24/2023 MINA HABILI
Corrections Issued 2/27/2023 MINA HABILI
Plan Check Approved 9/28/2023 ANDREW SANTIAGO
Issued 11/9/2023 APPLICANT
CofO in Progress 12/12/2024 OGANES TARAKHCHYAN
Permit Finaled 12/14/2024 RUBEN SALAS
CofO Issued 12/14/2024 RUBEN SALAS
Permit Finaled 12/14/2024 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 6/26/2023 NADER ISKANDER

Contact Information

Contractor La Top Builders Inc; Lic. No.: 1077576-B       ,
Engineer Lacher,, Todd Lee; Lic. No.: NA67656       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/31/2024 Approved KIRK SANDERS
Gunite 1/31/2024 Approved KIRK SANDERS
Pre-Gunite 1/31/2024 Approved KIRK SANDERS
Rough-Electrical 1/31/2024 Corrections Issued KIRK SANDERS
Rough-Plumbing 1/31/2024 Approved KIRK SANDERS
Deputy Shotcrete 2/2/2024 Conditional Approval DAVID MATSON
Rough-Electrical 3/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Gas Piping or Gas Test 3/21/2024 Approved ROBERTO PALACIOS-LOPEZ
Deck 4/8/2024 Approved CHRISTOPHE COCHRAN
Enclosure/Fence 4/8/2024 Corrections Issued CHRISTOPHE COCHRAN
Enclosure/Fence 6/13/2024 Corrections Issued OGANES TARAKHCHYAN
Enclosure/Fence 6/20/2024 Not Ready for Inspection JOHN COLEMAN
Enclosure/Fence 7/5/2024 Partial Inspection JOSE AVILA
SGSOV-Seismic Gas S/O Valve 7/5/2024 SGSOV Not Ready JOSE AVILA
Pool Equipment Noise Test 7/10/2024 Approved FELIPE PENICHE
Final 7/26/2024 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 7/26/2024 SGSOV Not Ready OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 8/2/2024 SGSOV Not Ready SALVADOR MARTINEZ
Enclosure/Fence 8/5/2024 Corrections Issued MISAEL ESPARZA
Pre-Inspection 8/5/2024 Partial Inspection MISAEL ESPARZA
Final 9/17/2024 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 9/17/2024 SGSOV Not Ready OGANES TARAKHCHYAN
Final 11/20/2024 OK to Issue CofO OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 11/20/2024 SGSOV Approved OGANES TARAKHCHYAN