10363 N RUFFNER AVE 91344
Certificate Information: 10363 N RUFFNER AVE 91344
- Application / Permit
- 23047-20000-00220
- Plan Check / Job No.
- B23VN01677
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- eplan NEW CONSTRUCTION 15'X32' POOL, SPA, BAJA, and 8'x17' FIRE PIT.
- Permit Issued
- Issued on 9/22/2023
- Issuing Office
- Current Status
- CofO Issued on 12/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2023 | JASON JANGADA |
| Corrections Issued | 2/12/2023 | JASON JANGADA |
| Applicant returned to address corrections | 9/1/2023 | JOHNPAUL ISIP |
| Plan Check Approved | 9/20/2023 | JOHNPAUL ISIP |
| Issued | 9/22/2023 | APPLICANT |
| CofO in Progress | 12/2/2024 | RAUL OLAGI |
| Permit Finaled | 12/12/2024 | RUBEN SALAS |
| CofO Issued | 12/12/2024 | RUBEN SALAS |
| Permit Finaled | 12/12/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/1/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 2/16/2024 | Approved | JAVIER RAMOS JR |
| Rough-Electrical | 2/16/2024 | Partial Approval | JAVIER RAMOS JR |
| Rough-Plumbing | 2/16/2024 | Approved | JAVIER RAMOS JR |
| Deputy Shotcrete | 2/23/2024 | Conditional Approval | ROBERT GOLD |
| Grounding or Bonding | 3/14/2024 | Approved | JAVIER RAMOS JR |
| Enclosure/Fence | 5/20/2024 | Corrections Issued | JAVIER RAMOS JR |
| Enclosure/Fence | 5/22/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 11/18/2024 | Approved | MISAEL ESPARZA |
| Final | 11/18/2024 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 11/18/2024 | SGSOV Not Ready | MISAEL ESPARZA |
| Final | 11/21/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 11/21/2024 | SGSOV Approved | JAVIER RAMOS JR |
| Pool Equipment Noise Test | 11/26/2024 | Approved | AGUSTIN ALVAREZMORALES |
| Final | 12/2/2024 | OK to Issue CofO | RAUL OLAGI |
| Enclosure/Fence | 12/3/2024 | Approved | JAVIER RAMOS JR |