8414 N ENCINO AVE 91325

Certificate Information: 8414 N ENCINO AVE 91325

Application / Permit
23047-20000-00219
Plan Check / Job No.
B23VN01658
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 34'-7" x 70' POOL/SPA W/ BAJA AND SUNKEN SEATING AREA PER ENGINEERING DESIGN
Permit Issued
Issued on 8/8/2023
Issuing Office
Valley
Current Status
CofO Issued on 12/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/9/2023 APPLICANT
Assigned to Plan Check Engineer 2/23/2023 SEAN SHAHMIRI
Corrections Issued 3/6/2023 SEAN SHAHMIRI
Quality Review Completed 3/8/2023 OMID HEDAYAT
Building Plans Picked Up 3/9/2023 APPLICANT
Applicant returned to address corrections 5/16/2023 SEAN SHAHMIRI
Applicant returned to address corrections 7/27/2023 SEAN SHAHMIRI
Plan Check Approved 8/7/2023 SEAN SHAHMIRI
Issued 8/8/2023 APPLICANT
CofO in Progress 11/17/2025 CHRISTOPHER ROJAS
Permit Finaled 12/2/2025 RUBEN SALAS
CofO Issued 12/2/2025 RUBEN SALAS
Permit Finaled 12/2/2025 RUBEN SALAS

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 5/17/2024 Partial Approval JAVIER RAMOS JR
Deputy Shotcrete 5/21/2024 Conditional Approval ROBERT GOLD
Pool Piping 6/6/2024 Approved JAVIER RAMOS JR
Grounding or Bonding 6/24/2025 Approved NICHOLAS TROWBRIDGE
Pre-Inspection 10/9/2025 Partial Inspection NICHOLAS TROWBRIDGE
Pool Equipment Noise Test 10/28/2025 Approved ALFREDO FLORES
Excavation/Setback/Form/Re-Bar 10/31/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 10/31/2025 Corrections Issued CHRISTOPHER ROJAS
Pre-Gunite 10/31/2025 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 10/31/2025 SGSOV Not Ready CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 11/14/2025 Approved CHRISTOPHER ROJAS
Final 11/14/2025 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 11/14/2025 SGSOV Not Ready CHRISTOPHER ROJAS
Final 11/17/2025 OK to Issue CofO CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 11/17/2025 SGSOV Approved CHRISTOPHER ROJAS