3615 N DIXIE CANYON AVE 91423
Certificate Information: 3615 N DIXIE CANYON AVE 91423
- Application / Permit
- 23047-20000-00087
- Plan Check / Job No.
- B23VN00483
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- PROPOSED NEW 10' X 14' SWIMMING POOL W/ BAJA PER CITY STD PLAN #265. SEE COMMENTS.
- Permit Issued
- Issued on 2/14/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/17/2023 | SERGIO MUNIZ |
| Corrections Issued | 1/17/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 1/26/2023 | APPLICANT |
| Issued | 2/14/2023 | APPLICANT |
| CofO in Progress | 8/12/2023 | MISAEL ESPARZA |
| Permit Finaled | 9/27/2023 | RUBEN SALAS |
| CofO Issued | 9/27/2023 | RUBEN SALAS |
| Permit Finaled | 9/27/2023 | RUBEN SALAS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Gwp Services; Lic. No.: 974163-C53 | 5632 VAN NUYS BLVD #427 VAN NUYS, CA 91401 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/5/2023 | Approved | MISAEL ESPARZA |
| Gas Piping or Gas Test | 4/7/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Rough-Electrical | 4/7/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Rough-Plumbing | 4/7/2023 | Partial Approval | MISAEL ESPARZA |
| Pre-Gunite | 4/13/2023 | Approved | JACK KARGODORIAN |
| Rough-Plumbing | 4/13/2023 | Approved | JACK KARGODORIAN |
| Deck | 4/25/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Gas Piping or Gas Test | 4/25/2023 | Corrections Issued | MISAEL ESPARZA |
| Rough-Plumbing | 4/25/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Deck | 5/2/2023 | Partial Approval | MISAEL ESPARZA |
| Gas Piping or Gas Test | 5/2/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Grounding or Bonding | 5/2/2023 | Partial Approval | MISAEL ESPARZA |
| Gas Piping or Gas Test | 5/9/2023 | Partial Approval | MISAEL ESPARZA |
| Grounding or Bonding | 5/9/2023 | Partial Approval | MISAEL ESPARZA |
| Grounding or Bonding | 5/13/2023 | Off-Hour Fees Due | |
| Enclosure/Fence | 5/19/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| Grounding or Bonding | 5/19/2023 | Approved | JUAN VALENZUELA |
| Pool Piping | 5/19/2023 | Approved | JUAN VALENZUELA |
| Enclosure/Fence | 5/23/2023 | Approved | JOHN COLEMAN |
| Pre-Inspection | 5/23/2023 | Approved | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 6/5/2023 | Approved | JACK KARGODORIAN |
| Gas Piping or Gas Test | 6/5/2023 | Approved | JACK KARGODORIAN |
| Pool/Spa Cover | 6/5/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 6/5/2023 | SGSOV Approved | JACK KARGODORIAN |
| Equipment Noise Level | 6/6/2023 | Approved | FELIPE PENICHE |
| ELECTRICAL-Final | 6/8/2023 | Approved | JOHN COLEMAN |
| PLUMBING-Final | 6/8/2023 | Approved | JOHN COLEMAN |
| Final | 8/11/2023 | OK to Issue CofO | MISAEL ESPARZA |