10911 N HASKELL AVE 91344
Certificate Information: 10911 N HASKELL AVE 91344
- Application / Permit
- 23047-10000-01932
- Plan Check / Job No.
- B23LA23824
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New pool/spa/baja/bbq bar per standard plan and engineer detail
- Permit Issued
- Issued on 2/8/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2023 | SHANGQIN XIE |
| Corrections Issued | 12/18/2023 | SHANGQIN XIE |
| Plan Check Approved | 1/24/2024 | KHUONG TRUONG |
| Issued | 2/8/2024 | APPLICANT |
| CofO in Progress | 6/27/2025 | JAVIER RAMOS JR |
| Permit Finaled | 7/31/2025 | RUBEN SALAS |
| CofO Issued | 7/31/2025 | RUBEN SALAS |
| Permit Finaled | 7/31/2025 | RUBEN SALAS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 5/8/2024 | Approved | JAVIER RAMOS JR |
| Special/Order Compliance | 5/8/2024 | Corrections Issued | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 7/11/2024 | Corrections Issued | JAVIER RAMOS JR |
| Rough-Mechanical | 7/25/2024 | Approved | DAVID ANDERSON |
| Deck | 8/21/2024 | Corrections Issued | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 8/30/2024 | Partial Approval | JAVIER RAMOS JR |
| Deck | 1/9/2025 | Approved | JAVIER RAMOS JR |
| Deputy Shotcrete | 1/9/2025 | Conditional Approval | JAVIER RAMOS JR |
| Enclosure/Fence | 1/9/2025 | Corrections Issued | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 1/9/2025 | Approved | JAVIER RAMOS JR |
| Grounding or Bonding | 1/9/2025 | Approved | JAVIER RAMOS JR |
| Enclosure/Fence | 6/20/2025 | Approved | JAVIER RAMOS JR |
| Final | 6/20/2025 | Corrections Issued | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 6/20/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Equipment Noise Level | 6/25/2025 | Approved | ALFREDO FLORES |
| Final | 6/27/2025 | OK to Issue CofO | JAVIER RAMOS JR |