737 N SARBONNE ROAD 90077

Certificate Information: 737 N SARBONNE ROAD 90077

Application / Permit
23047-10000-01789
Plan Check / Job No.
B23LA21956
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
eplan 1. New Pool & Spa, 46'-6" X 21'-4 1/4".
Permit Issued
Issued on 4/17/2024
Issuing Office
Current Status
Issued on 4/17/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/20/2023 APPLICANT
Assigned to Plan Check Engineer 12/7/2023 ADRIANA LOPEZ
Corrections Issued 12/20/2023 ADRIANA LOPEZ
Quality Review Completed 1/12/2024 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 1/24/2024 ADRIANA LOPEZ
Applicant returned to address corrections 2/16/2024 ADRIANA LOPEZ
Applicant returned to address corrections 4/2/2024 ADRIANA LOPEZ
Plan Check Approved 4/15/2024 ADRIANA LOPEZ
Issued 4/17/2024 APPLICANT

Permit Application Clearance Information

Miscellaneous Cleared 1/25/2024 MAYELA VILLA
Excavation more than 5-ft deep Cleared 4/2/2024 CALOSHA APPROVED

Contact Information

Contractor Siboni Development & Design Inc; Lic. No.: 1085971-B       ,
Engineer Eftekhari,, Hossein; Lic. No.: C50121 5945 SETTLER COURT      ANAHEIM, CA 92807
Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 9/18/2024 Not Ready for Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 9/20/2024 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 9/20/2024 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 1/2/2025 Not Ready for Inspection CHRISTOPHER WILSON
Rough-Electrical 1/2/2025 Not Ready for Inspection CHRISTOPHER WILSON
Rough-Plumbing 1/2/2025 Not Ready for Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 1/13/2025 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 1/28/2025 Not Ready for Inspection CHRISTOPHER WILSON
Pre-Gunite 1/28/2025 Corrections Issued CHRISTOPHER WILSON
Rough-Electrical 1/28/2025 Not Ready for Inspection CHRISTOPHER WILSON
Rough-Plumbing 1/28/2025 Not Ready for Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 2/18/2025 Corrections Issued SEAN HAUPT
Rough-Electrical 2/18/2025 Not Ready for Inspection SEAN HAUPT
Rough-Plumbing 2/18/2025 Not Ready for Inspection SEAN HAUPT
Pre-Gunite 2/20/2025 Partial Approval CHRISTOPHER WILSON
Rough-Electrical 2/20/2025 Partial Approval CHRISTOPHER WILSON
Rough-Plumbing 2/20/2025 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 4/28/2025 Partial Approval CHRISTOPHER WILSON
Rough-Electrical 3/9/2026 No Access for Inspection CHRISTOPHER WILSON
Rough-Plumbing 3/9/2026 No Access for Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 3/12/2026 Partial Approval CHRISTOPHER WILSON
Rough-Plumbing 3/12/2026 Partial Approval CHRISTOPHER WILSON
Deputy Shotcrete 3/17/2026 Conditional Approval ANDREW NAVE
Pre-Gunite 5/21/2026 Approved RYAN SALAZAR
Rough-Electrical 5/21/2026 Approved RYAN SALAZAR
Rough-Plumbing 5/21/2026 Approved RYAN SALAZAR