737 N SARBONNE ROAD 90077
Certificate Information: 737 N SARBONNE ROAD 90077
- Application / Permit
- 23047-10000-01789
- Plan Check / Job No.
- B23LA21956
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- eplan 1. New Pool & Spa, 46'-6" X 21'-4 1/4".
- Permit Issued
- Issued on 4/17/2024
- Issuing Office
- Current Status
- Issued on 4/17/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/7/2023 | ADRIANA LOPEZ |
| Corrections Issued | 12/20/2023 | ADRIANA LOPEZ |
| Quality Review Completed | 1/12/2024 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 1/24/2024 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 2/16/2024 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 4/2/2024 | ADRIANA LOPEZ |
| Plan Check Approved | 4/15/2024 | ADRIANA LOPEZ |
| Issued | 4/17/2024 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 1/25/2024 | MAYELA VILLA |
| Excavation more than 5-ft deep | Cleared | 4/2/2024 | CALOSHA APPROVED |
Contact Information
| Contractor | Siboni Development & Design Inc; Lic. No.: 1085971-B | , |
| Engineer | Eftekhari,, Hossein; Lic. No.: C50121 | 5945 SETTLER COURT ANAHEIM, CA 92807 |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 9/18/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 9/20/2024 | Partial Approval | CHRISTOPHER WILSON |
| Piling/Pier/Caisson | 9/20/2024 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 1/2/2025 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Rough-Electrical | 1/2/2025 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Rough-Plumbing | 1/2/2025 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 1/13/2025 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 1/28/2025 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Pre-Gunite | 1/28/2025 | Corrections Issued | CHRISTOPHER WILSON |
| Rough-Electrical | 1/28/2025 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Rough-Plumbing | 1/28/2025 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 2/18/2025 | Corrections Issued | SEAN HAUPT |
| Rough-Electrical | 2/18/2025 | Not Ready for Inspection | SEAN HAUPT |
| Rough-Plumbing | 2/18/2025 | Not Ready for Inspection | SEAN HAUPT |
| Pre-Gunite | 2/20/2025 | Partial Approval | CHRISTOPHER WILSON |
| Rough-Electrical | 2/20/2025 | Partial Approval | CHRISTOPHER WILSON |
| Rough-Plumbing | 2/20/2025 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 4/28/2025 | Partial Approval | CHRISTOPHER WILSON |
| Rough-Electrical | 3/9/2026 | No Access for Inspection | CHRISTOPHER WILSON |
| Rough-Plumbing | 3/9/2026 | No Access for Inspection | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 3/12/2026 | Partial Approval | CHRISTOPHER WILSON |
| Rough-Plumbing | 3/12/2026 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Shotcrete | 3/17/2026 | Conditional Approval | ANDREW NAVE |
| Pre-Gunite | 5/21/2026 | Approved | RYAN SALAZAR |
| Rough-Electrical | 5/21/2026 | Approved | RYAN SALAZAR |
| Rough-Plumbing | 5/21/2026 | Approved | RYAN SALAZAR |