3171 N GLENMANOR PL 90039

Certificate Information: 3171 N GLENMANOR PL 90039

Application / Permit
23047-10000-01562
Plan Check / Job No.
B23LA18416
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL AND SPA WITH WATER FEATURE. DETAILS 271 AND STANDARD PLAN 268
Permit Issued
Issued on 10/31/2023
Issuing Office
Metro
Current Status
CofO Issued on 5/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/2/2023 APPLICANT
Assigned to Plan Check Engineer 10/8/2023 AUNG SOE
Corrections Issued 10/10/2023 AUNG SOE
Building Plans Picked Up 10/12/2023 APPLICANT
Plan Check Approved 10/26/2023 KHUONG TRUONG
Issued 10/31/2023 APPLICANT
CofO in Progress 4/19/2024 HAMIK HARTOUNIAN
CofO Issued 5/15/2024 DEROLD HAUFF
Permit Finaled 5/15/2024 DEROLD HAUFF

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Legacy Builders & Remodeling Inc; Lic. No.: 1046784-B 9507 DORK ST      PICO RIVERA, CA 90660
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/17/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Pool Piping 11/17/2023 Approved HAMIK HARTOUNIAN
Rough-Electrical 11/17/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Grading Pre-Inspection 11/21/2023 Approved ROY SPAULDING
Gunite 11/21/2023 Approved ROY SPAULDING
Rough-Electrical 11/21/2023 Approved ROY SPAULDING
Deputy Shotcrete 11/28/2023 Conditional Approval HAMIK HARTOUNIAN
Enclosure/Fence 3/7/2024 Approved HAMIK HARTOUNIAN
Pool Equipment Noise Test 3/19/2024 Approved JUAN ESCOTO DELGADO
Excavation/Setback/Form/Re-Bar 4/5/2024 Approved HAMIK HARTOUNIAN
Final 4/5/2024 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 4/5/2024 SGSOV Not Ready HAMIK HARTOUNIAN
Final 4/18/2024 OK to Issue CofO HAMIK HARTOUNIAN
Pre-Gunite 4/18/2024 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 4/18/2024 SGSOV Approved HAMIK HARTOUNIAN