5417 N BURNET AVE 91411
Certificate Information: 5417 N BURNET AVE 91411
- Application / Permit
- 23047-10000-01547
- Plan Check / Job No.
- B23LA18251
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ePlan. New Pool per LA City Standard Plan
- Permit Issued
- Issued on 2/14/2024
- Issuing Office
- Current Status
- CofO Issued on 9/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2023 | MICHAEL LANZONE |
| Corrections Issued | 10/3/2023 | MICHAEL LANZONE |
| Applicant returned to address corrections | 1/8/2024 | FERNANDO FLORES |
| Plan Check Approved | 1/27/2024 | FERNANDO FLORES |
| Issued | 2/14/2024 | APPLICANT |
| CofO in Progress | 6/13/2024 | JACK KARGODORIAN |
| CofO Issued | 9/5/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/5/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 12/7/2023 | RIDWAN HARDY |
| ZI | Cleared | 12/12/2023 | STEVEN WECHSLER |
Contact Information
| Contractor | La Top Builders Inc; Lic. No.: 1077576-B | , |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: NA86051 | , |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/7/2024 | Corrections Issued | THOMAS FINNILA |
| Pre-Gunite | 3/7/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Rough-Electrical | 3/7/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Rough-Plumbing | 3/7/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Pre-Gunite | 3/8/2024 | Conditional Approval | THOMAS FINNILA |
| Pre-Inspection | 3/8/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Rough-Plumbing | 3/8/2024 | Corrections Issued | THOMAS FINNILA |
| Gas Piping or Gas Test | 3/26/2024 | Corrections Issued | THOMAS FINNILA |
| Rough-Plumbing | 3/26/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Deck | 4/12/2024 | Corrections Issued | THOMAS FINNILA |
| Enclosure/Fence | 5/7/2024 | Corrections Issued | THOMAS FINNILA |
| Grounding or Bonding | 5/7/2024 | Corrections Issued | THOMAS FINNILA |
| Deck | 5/14/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Enclosure/Fence | 5/14/2024 | Corrections Issued | MISAEL ESPARZA |
| Deck | 5/20/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Enclosure/Fence | 5/20/2024 | Corrections Issued | JACK KARGODORIAN |
| Deck | 5/24/2024 | Corrections Issued | JACK KARGODORIAN |
| Enclosure/Fence | 5/24/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Deck | 5/29/2024 | Approved | JACK KARGODORIAN |
| Enclosure/Fence | 5/29/2024 | Approved | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 6/12/2024 | Approved | JACK KARGODORIAN |
| Final | 6/12/2024 | OK to Issue CofO | JACK KARGODORIAN |
| Pre-Gunite | 6/12/2024 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 6/12/2024 | SGSOV Approved | JACK KARGODORIAN |