23726 W WELBY WAY 91307

Certificate Information: 23726 W WELBY WAY 91307

Application / Permit
23047-10000-01518
Plan Check / Job No.
B23LA17841
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW IRREGULAR SHAPED 22'-0" X 28'-6" POOL WITH BAJA PER STANDARD PLAN 268
Permit Issued
Issued on 12/14/2023
Issuing Office
Valley
Current Status
CofO Issued on 8/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/22/2023 APPLICANT
Assigned to Plan Check Engineer 9/22/2023 MICHAEL LANZONE
Corrections Issued 9/22/2023 MICHAEL LANZONE
Plan Check Approved 12/14/2023 ALEC MOUSAKHANIAN
Issued 12/14/2023 APPLICANT
CofO in Progress 7/19/2024 GEVORK IPCHYAN
Permit Finaled 8/1/2024 JOHN JANSON
CofO Issued 8/1/2024 JOHN JANSON
Permit Finaled 8/1/2024 JOHN JANSON

Permit Application Clearance Information

Construction near power lines Cleared 12/12/2023 WALTER RAMIREZ

Contact Information

Contractor Noga Pool And Spa Inc; Lic. No.: 946647-C53 5739 KANAN ROAD #639      AGOURA HILLS, CA 91301
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 1/10/2024 Not Ready for Inspection MORRIS JACKSON
Pre-Gunite 1/10/2024 Approved MORRIS JACKSON
Gas Piping or Gas Test 1/16/2024 Approved JEFFREY PARD
Pool Piping 1/16/2024 Approved JEFFREY PARD
Deputy Shotcrete 1/17/2024 Conditional Approval HORACE FULTZ
Grounding or Bonding 3/5/2024 Approved GEVORK IPCHYAN
Enclosure/Fence 5/28/2024 Approved GEVORK IPCHYAN
Excavation/Setback/Form/Re-Bar 6/17/2024 Approved GEVORK IPCHYAN
Final 6/17/2024 Corrections Issued GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 6/17/2024 SGSOV Approved GEVORK IPCHYAN
Pool Equipment Noise Test 6/20/2024 Approved ALFREDO FLORES
ELECTRICAL-Final 7/16/2024 Approved GEVORK IPCHYAN
Final 7/16/2024 Partial Approval GEVORK IPCHYAN
Final 7/18/2024 OK to Issue CofO GEVORK IPCHYAN