3580 S WASATCH AVE 90066
Certificate Information: 3580 S WASATCH AVE 90066
- Application / Permit
- 23047-10000-01497
- Plan Check / Job No.
- B23LA17690
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ePlan: New swimming pool and spa per standard plan. ***1 of 2***
- Permit Issued
- Issued on 12/22/2023
- Issuing Office
- Current Status
- CofO Issued on 2/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/11/2023 | CAROLEAN BASMA |
| Corrections Issued | 12/12/2023 | CAROLEAN BASMA |
| Plan Check Approved | 12/22/2023 | CAROLEAN BASMA |
| Issued | 12/22/2023 | APPLICANT |
| Permit Finaled | 2/28/2025 | RICHARD STEINBACH |
| CofO Issued | 2/28/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/28/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Martinko Construction Inc; Lic. No.: 990964-B | , |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 1/31/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Deputy Shotcrete | 2/2/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Deck | 3/12/2024 | Approved | JESUS RODRIGUEZ |
| Rough-Electrical | 3/14/2024 | Approved | JESUS RODRIGUEZ |
| Gas Piping or Gas Test | 3/18/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Gas Piping or Gas Test | 3/19/2024 | Approved | JESUS RODRIGUEZ |
| Deck | 3/28/2024 | Partial Approval | KENNETH NAGLE |
| Grounding or Bonding | 3/28/2024 | Partial Approval | KENNETH NAGLE |
| Enclosure/Fence | 11/18/2024 | Approved | JESUS PINEDA |
| Pool Equipment Noise Test | 12/11/2024 | Approved | EUSEBIO GUZMAN |
| Excavation/Setback/Form/Re-Bar | 1/16/2025 | Approved | JESUS PINEDA |
| Final | 1/16/2025 | Partial Approval | JESUS PINEDA |
| Pre-Gunite | 1/16/2025 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 1/16/2025 | SGSOV Approved | JESUS PINEDA |