525 N BELLAGIO TER 90049
Certificate Information: 525 N BELLAGIO TER 90049
- Application / Permit
- 23047-10000-01480
- Plan Check / Job No.
- B23LA17493
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- SUPPLEMENTAL TO: 22014-10000-03715. REVISION TO POOL STRUCTURAL PLANS TO ADD MISSING DETAILS
- Permit Issued
- Issued on 9/30/2023
- Issuing Office
- Current Status
- CofO Issued on 12/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2023 | JAD BASMA |
| Plan Check Approved | 9/27/2023 | JAD BASMA |
| No Progress | 9/27/2023 | JAD BASMA |
| Plan Check Approved | 9/27/2023 | JAD BASMA |
| Plan Check Approved | 9/29/2023 | Jasmine Dent |
| Issued | 9/30/2023 | APPLICANT |
| CofO in Progress | 12/10/2024 | CARLOS MATAMOROS |
| Permit Finaled | 12/17/2024 | RICHARD STEINBACH |
| CofO Issued | 12/17/2024 | RICHARD STEINBACH |
| Permit Finaled | 12/17/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Hanover Builders Inc; Lic. No.: 709353-B | 141 DUESENBERG DRIVE STE 6 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grounding or Bonding | 10/4/2023 | Approved | CARLOS MATAMOROS |
| Pool Piping | 10/4/2023 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 10/13/2023 | Partial Approval | CARLOS MATAMOROS |
| Grounding or Bonding | 1/4/2024 | Partial Approval | CARLOS MATAMOROS |
| Grounding or Bonding | 3/20/2024 | Approved | CARLOS MATAMOROS |
| Enclosure/Fence | 7/23/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Enclosure/Fence | 8/7/2024 | Corrections Issued | CARLOS MATAMOROS |
| Enclosure/Fence | 8/12/2024 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 11/15/2024 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 11/15/2024 | Approved | CARLOS MATAMOROS |
| Final | 11/15/2024 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Final | 11/15/2024 | Approved | CARLOS MATAMOROS |
| Pre-Gunite | 11/15/2024 | Approved | CARLOS MATAMOROS |
| Final | 12/9/2024 | OK to Issue CofO | CARLOS MATAMOROS |