4906 N VAN NOORD AVE 91423

Certificate Information: 4906 N VAN NOORD AVE 91423

Application / Permit
23047-10000-01463
Plan Check / Job No.
B23LA17200
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
ePlan Resize the existing pool to 15'WX22'Lx5'D pool and 6'Wx6'LX4'D spa per engineer
Permit Issued
Issued on 1/18/2024
Issuing Office
Current Status
CofO Issued on 3/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/14/2023 APPLICANT
Assigned to Plan Check Engineer 9/19/2023 KHUONG TRUONG
Corrections Issued 9/20/2023 KHUONG TRUONG
Applicant returned to address corrections 10/11/2023 JOSEPH RAFOLS
Plan Check Approved 10/15/2023 KHUONG TRUONG
Issued 1/18/2024 APPLICANT
CofO in Progress 1/24/2025 OGANES TARAKHCHYAN
Permit Finaled 3/18/2025 RUBEN SALAS
Permit Finaled 3/18/2025 RUBEN SALAS
CofO Issued 3/18/2025 RUBEN SALAS

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Lantern Hills Construction Co.; Lic. No.: 1055902-B       ,
Engineer Samadzadeh,, Hooman Ali; Lic. No.: C87661 22430 CRISWELL ST      WEST HILLS, CA 91307

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/29/2024 Conditional Approval JUAN VALENZUELA
Pool Piping 4/1/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Pre-Gunite 4/1/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Rough-Electrical 4/1/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Pre-Gunite 4/8/2024 Approved DAVID ANDERSON
Rough-Electrical 4/8/2024 Partial Approval DAVID ANDERSON
Rough-Plumbing 4/8/2024 Partial Approval DAVID ANDERSON
Deputy Other (see comments) 4/10/2024 Conditional Approval JUAN VALENZUELA
Deputy Other (see comments) 4/16/2024 Conditional Approval JUAN VALENZUELA
Rough-Plumbing 5/14/2024 Corrections Issued OGANES TARAKHCHYAN
Gas Piping or Gas Test 5/20/2024 Approved OGANES TARAKHCHYAN
Rough-Plumbing 5/20/2024 Partial Approval OGANES TARAKHCHYAN
Rough-Plumbing 5/22/2024 Corrections Issued OGANES TARAKHCHYAN
Final 10/29/2024 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 10/29/2024 SGSOV Not Ready OGANES TARAKHCHYAN
Pool Equipment Noise Test 11/14/2024 Approved FELIPE PENICHE
Final 11/21/2024 Partial Approval OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 11/21/2024 SGSOV Approved OGANES TARAKHCHYAN
Final 12/10/2024 OK to Issue CofO OGANES TARAKHCHYAN
Deck 3/10/2025 Approved OGANES TARAKHCHYAN
Enclosure/Fence 3/10/2025 Approved OGANES TARAKHCHYAN