748 S CLOVERDALE AVE 90036
Certificate Information: 748 S CLOVERDALE AVE 90036
- Application / Permit
- 23047-10000-01312
- Plan Check / Job No.
- B23LA15400
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW SWIMMING POOL WITH INTERIOR SPA. WORK PER LADBS STANDARD PLAN #242 AND ENGINEERING DETAILS.
- Permit Issued
- Issued on 6/3/2024
- Issuing Office
- Current Status
- CofO Issued on 11/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/20/2023 | ALFRED RAMIREZ |
| Corrections Issued | 9/21/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 10/11/2023 | ROSENDO MEDINA |
| Issued | 6/3/2024 | APPLICANT |
| CofO in Progress | 9/19/2024 | JOSE MACIAS |
| CofO in Progress | 10/28/2024 | JOAQUIN GREENOUGH |
| CofO in Progress | 11/15/2024 | JOAQUIN GREENOUGH |
| Permit Finaled | 11/16/2024 | DEROLD HAUFF |
| CofO Issued | 11/16/2024 | DEROLD HAUFF |
| Permit Finaled | 11/16/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| "Q" conditions | Cleared | 10/6/2023 | YINGSHI HUANG |
| HPOZ | Cleared | 10/6/2023 | YINGSHI HUANG |
| ZA Case | Cleared | 10/6/2023 | YINGSHI HUANG |
| Hold | Not Cleared | 1/2/2025 | Department of Building and Safety |
Contact Information
| Contractor | Avcad Construction; Lic. No.: 641900-B | 915 S BERENDO STREET 2 LOS ANGELES, CA 90006 |
| Engineer | Shniderman,, Jason Bernard; Lic. No.: C20524 | 16000 SHERMAN WAY #234 VAN NUYS, CA 91607 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/26/2024 | Corrections Issued | AMIR NAZARIAN |
| Grounding or Bonding | 6/26/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Pre-Gunite | 6/26/2024 | Corrections Issued | AMIR NAZARIAN |
| Rough-Plumbing | 6/26/2024 | Corrections Issued | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 6/26/2024 | SGSOV Not Ready | AMIR NAZARIAN |
| Pre-Inspection | 6/27/2024 | Corrections Issued | AMIR NAZARIAN |
| Deputy Shotcrete | 7/10/2024 | No Access for Inspection | AMIR NAZARIAN |
| ELECTRICAL-Final | 9/18/2024 | Approved | JOSE MACIAS |
| Excavation/Setback/Form/Re-Bar | 9/18/2024 | Approved | JOSE MACIAS |
| Final | 9/18/2024 | Not Ready for Inspection | JOSE MACIAS |
| PLUMBING-Final | 9/18/2024 | Approved | JOSE MACIAS |
| Pre-Gunite | 9/18/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 9/18/2024 | SGSOV Approved | JOSE MACIAS |
| Final | 10/30/2024 | Corrections Issued | JOSE MACIAS |
| Equipment Noise Level | 11/6/2024 | Approved | ANDEY CHAPARRO |
| Final | 11/15/2024 | OK to Issue CofO | JOAQUIN GREENOUGH |