5437 N KATHERINE AVE 91401
Certificate Information: 5437 N KATHERINE AVE 91401
- Application / Permit
- 23047-10000-01183
- Plan Check / Job No.
- B23LA13615
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- eplan PROPOSED SWIMMING POOL AND SPA PER STD PLAN #268 WITH AUTOMATIC POOL COVER.
- Permit Issued
- Issued on 12/21/2023
- Issuing Office
- Current Status
- CofO Issued on 4/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/3/2023 | MICHAEL LOPEZ |
| Corrections Issued | 8/3/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 11/28/2023 | MICHAEL LOPEZ |
| Plan Check Approved | 12/3/2023 | MICHAEL LOPEZ |
| Issued | 12/21/2023 | APPLICANT |
| CofO in Progress | 4/5/2024 | RYAN SALAZAR |
| Permit Finaled | 4/10/2024 | RUBEN SALAS |
| CofO Issued | 4/10/2024 | RUBEN SALAS |
| Permit Finaled | 4/10/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/3/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Catak Pools; Lic. No.: 1048881-C53 | 1197 E LOS ANGELES AVE #C195 SIMI VALLEY, CA 93065 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/17/2024 | Approved | RYAN SALAZAR |
| Gas Piping or Gas Test | 1/17/2024 | Approved | RYAN SALAZAR |
| Pool Piping | 1/17/2024 | Approved | RYAN SALAZAR |
| Pre-Gunite | 1/17/2024 | Approved | RYAN SALAZAR |
| Rough-Electrical | 1/17/2024 | Approved | RYAN SALAZAR |
| Rough-Plumbing | 1/17/2024 | Approved | RYAN SALAZAR |
| Deputy Shotcrete | 1/25/2024 | Conditional Approval | JUAN VALENZUELA |
| Grounding or Bonding | 2/14/2024 | Approved | RYAN SALAZAR |
| Enclosure/Fence | 2/26/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 3/14/2024 | Approved | RYAN SALAZAR |
| Final | 3/14/2024 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Final | 3/14/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 3/14/2024 | SGSOV Approved | RYAN SALAZAR |
| Equipment Noise Level | 3/19/2024 | Approved | ALFREDO FLORES |
| Equipment Noise Level | 3/20/2024 | Approved | ALFREDO FLORES |
| Final | 4/5/2024 | OK to Issue CofO | RYAN SALAZAR |