1906 W ESCARPA DR 90041
Certificate Information: 1906 W ESCARPA DR 90041
- Application / Permit
- 23047-10000-01171
- Plan Check / Job No.
- B23LA13515
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- Eplan (N) 30'x20' POOL w/ 7'x7' SPA. 7' max depth POOL PER STANDARD PLAN #268
- Permit Issued
- Issued on 2/1/2024
- Issuing Office
- Current Status
- CofO Issued on 6/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/27/2023 | ADRIANA LOPEZ |
| Corrections Issued | 8/5/2023 | ADRIANA LOPEZ |
| Quality Review Completed | 8/16/2023 | FARUK SEZER |
| Applicant returned to address corrections | 9/25/2023 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 12/13/2023 | ADRIANA LOPEZ |
| Plan Check Approved | 1/22/2024 | ADRIANA LOPEZ |
| Issued | 2/1/2024 | APPLICANT |
| CofO in Progress | 5/21/2025 | DAVID WILLIAMS |
| No Progress | 5/23/2025 | DEROLD HAUFF |
| CofO in Progress | 5/23/2025 | DEROLD HAUFF |
| Permit Finaled | 6/3/2025 | DEROLD HAUFF |
| Permit Finaled | 6/3/2025 | DEROLD HAUFF |
| CofO Issued | 6/3/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/6/2023 | JONATHAN HOM |
Contact Information
| Contractor | Pool Icons Inc; Lic. No.: 479446-C53 | PO BOX 246 LA HABRA, CA 90633 |
| Engineer | Tsao,, Tze-Tzong; Lic. No.: C46886 | 9428 ETON AVE STE M CHATSWORTH, CA 91311 |
| Geologist | Tsao,, Tze-Tzong; Lic. No.: EG1783 | 9428 ETON AVENUE #M CHATSWORTH, CA 91311 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 3/29/2024 | Approved | CRAIG VAUGHAN |
| Deck | 9/6/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Deck | 10/11/2024 | Approved | ROY SPAULDING |
| Enclosure/Fence | 2/19/2025 | Approved | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 4/3/2025 | Approved | DAVID WILLIAMS |
| Final | 4/3/2025 | Conditional Approval | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 4/3/2025 | SGSOV Approved | DAVID WILLIAMS |
| Deputy Shotcrete | 5/19/2025 | Approved | DAVID WILLIAMS |
| Final | 5/20/2025 | OK to Issue CofO | DAVID WILLIAMS |