1439 S EDRIS DR 90035

Certificate Information: 1439 S EDRIS DR 90035

Application / Permit
23047-10000-01163
Plan Check / Job No.
B23LA13466
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
Eplan NEW 20' X 10' POOL WITH 6'-9" X 6'-9" SPA PER STANDARD PLAN 268 AND ENGINER DETAIL **SEE COMMENTS**
Permit Issued
Issued on 11/13/2023
Issuing Office
Current Status
CofO Issued on 6/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/1/2023 APPLICANT
Assigned to Plan Check Engineer 8/8/2023 ALEC MOUSAKHANIAN
Corrections Issued 8/8/2023 ALEC MOUSAKHANIAN
Applicant returned to address corrections 9/22/2023 ALEC MOUSAKHANIAN
Applicant returned to address corrections 9/25/2023 GIOVANNY CHAVEZ
Plan Check Approved 9/27/2023 GIOVANNY CHAVEZ
Issued 11/13/2023 APPLICANT
CofO in Progress 6/13/2025 ARAM AVEDISIAN
Permit Finaled 6/17/2025 RICHARD STEINBACH
CofO Issued 6/17/2025 RICHARD STEINBACH
Permit Finaled 6/17/2025 RICHARD STEINBACH

Permit Application Clearance Information

Construction near power lines Cleared 9/19/2023 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 11/8/2024 Approved ASHLEY THOMPSON
Rough-Electrical 11/8/2024 Approved ASHLEY THOMPSON
Rough-Plumbing 11/8/2024 Partial Approval ASHLEY THOMPSON
Gas Piping or Gas Test 12/3/2024 Approved ASHLEY THOMPSON
Rough-Electrical 12/3/2024 Approved ASHLEY THOMPSON
Grounding or Bonding 12/26/2024 Partial Approval CHRISTOPHER WILSON
Enclosure/Fence 2/12/2025 Corrections Issued EVAN COOPER
Excavation/Setback/Form/Re-Bar 2/12/2025 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 2/12/2025 SGSOV Not Ready EVAN COOPER
Enclosure/Fence 4/23/2025 Corrections Issued EVAN COOPER
Rough-Electrical 4/23/2025 Corrections Issued EVAN COOPER
Enclosure/Fence 5/9/2025 Approved ARAM AVEDISIAN
Final 5/23/2025 Corrections Issued ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 5/23/2025 SGSOV Approved ASHLEY THOMPSON
Pool Equipment Noise Test 5/27/2025 Approved JUAN ESCOTO DELGADO
Final 6/11/2025 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Final 6/13/2025 Approved ARAM AVEDISIAN
Final 6/13/2025 OK to Issue CofO ARAM AVEDISIAN