11555 W BELLAGIO ROAD 90049

Certificate Information: 11555 W BELLAGIO ROAD 90049

Application / Permit
23047-10000-01101
Plan Check / Job No.
B23LA12794
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
ePlan Remodel (e) swimming pool , Add Pool Cover, Add Spa ALL WORK TO BE DONE INSIDE EXISTING SHELL PER STANDARD PLAN AND ENGINEER DETAIL
Permit Issued
Issued on 8/10/2023
Issuing Office
Current Status
CofO Issued on 9/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2023 APPLICANT
Assigned to Plan Check Engineer 7/21/2023 VICTOR CHEN
Corrections Issued 7/24/2023 VICTOR CHEN
Plan Check Approved 8/3/2023 KHUONG TRUONG
Issued 8/10/2023 APPLICANT
CofO in Progress 9/12/2025 CARLOS MATAMOROS
Permit Finaled 9/18/2025 RICHARD STEINBACH
CofO Issued 9/18/2025 RICHARD STEINBACH
Permit Finaled 9/18/2025 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/3/2023 VICTOR CHEN

Contact Information

Contractor Aqua Pool & Spa Construction Inc; Lic. No.: 1046115-C53 7361 ETHEL AVE #4      NORTH HOLLYWOOD, CA 91605
Engineer Cristescu,, Barbu Dan; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 9/12/2023 Not Ready for Inspection CARLOS MATAMOROS
Grounding or Bonding 9/13/2023 Approved CARLOS MATAMOROS
Pool Piping 9/13/2023 Approved CARLOS MATAMOROS
Pre-Gunite 9/13/2023 Approved CARLOS MATAMOROS
Rough-Electrical 9/13/2023 Approved CARLOS MATAMOROS
Rough-Plumbing 9/13/2023 Approved CARLOS MATAMOROS
Deputy Shotcrete 9/26/2023 Conditional Approval MICHAEL PELHAM
Special/Order Compliance 9/29/2023 Corrections Issued CARLOS MATAMOROS
Deck 11/16/2023 Approved CARLOS MATAMOROS
Gas Piping or Gas Test 9/23/2024 Approved CARLOS MATAMOROS
Enclosure/Fence 2/26/2025 Corrections Issued CARLOS MATAMOROS
Enclosure/Fence 3/5/2025 Approved CARLOS MATAMOROS
Equipment Noise Level 8/27/2025 Approved EUSEBIO GUZMAN
Pool Equipment Noise Test 8/27/2025 Approved EUSEBIO GUZMAN
Final 9/4/2025 Not Ready for Inspection DANIEL VERA
SGSOV-Seismic Gas S/O Valve 9/4/2025 SGSOV Not Ready DANIEL VERA
ELECTRICAL-Final 9/9/2025 Approved CARLOS MATAMOROS
Final 9/9/2025 Corrections Issued CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 9/9/2025 SGSOV Approved CARLOS MATAMOROS
ELECTRICAL-Final 9/11/2025 Approved CARLOS MATAMOROS
Final 9/11/2025 OK to Issue CofO CARLOS MATAMOROS
PLUMBING-Final 9/12/2025 Approved CARLOS MATAMOROS