147 N WINDSOR BLVD 90004
Certificate Information: 147 N WINDSOR BLVD 90004
- Application / Permit
- 23047-10000-01079
- Plan Check / Job No.
- B23LA12518
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) POOL PER CITY STANDARD PLAN
- Permit Issued
- Issued on 12/1/2023
- Issuing Office
- Current Status
- CofO Issued on 12/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/10/2023 | AUNG SOE |
| Corrections Issued | 7/18/2023 | AUNG SOE |
| Building Plans Picked Up | 7/19/2023 | APPLICANT |
| Applicant returned to address corrections | 9/29/2023 | MINA HABILI |
| Applicant returned to address corrections | 10/27/2023 | NEHEMIAS RAMOS |
| Plan Check Approved | 12/1/2023 | MINA HABILI |
| Issued | 12/1/2023 | APPLICANT |
| CofO in Progress | 12/18/2024 | JEFFREY MEAD |
| Permit Finaled | 12/29/2024 | DEROLD HAUFF |
| CofO Issued | 12/29/2024 | DEROLD HAUFF |
| Permit Finaled | 12/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 9/22/2023 | DANIEL CORONADO |
| CPC | Cleared | 9/22/2023 | DANIEL CORONADO |
| CPC | Cleared | 9/22/2023 | DANIEL CORONADO |
| Construction near power lines | Cleared | 9/22/2023 | WALTER RAMIREZ |
| Construction within easement | Cleared | 9/22/2023 | WALTER RAMIREZ |
| ZA Case | Cleared | 9/22/2023 | DANIEL CORONADO |
| HPOZ | Cleared | 9/25/2023 | DAMIAN GATTO |
Contact Information
| Contractor | Simply The Best; Lic. No.: 532135-B | 6517 LINDENHURST AVENUE LOS ANGELES, CA 90048 |
| Engineer | Azizisefat,, Solayman; Lic. No.: C57840 | 19510 VENTURA BLVD STE 110 TARZANA, CA 91356 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 10/4/2024 | Approved | ENRIQUE MIRELES |
| Deputy Shotcrete | 10/7/2024 | Partial Approval | JEFFREY MEAD |
| Deck | 11/21/2024 | Approved | JEFFREY MEAD |
| Enclosure/Fence | 11/21/2024 | Approved | JEFFREY MEAD |
| Pool Equipment Noise Test | 12/3/2024 | Approved | ANDEY CHAPARRO |
| Excavation/Setback/Form/Re-Bar | 12/4/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 12/4/2024 | Corrections Issued | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 12/4/2024 | SGSOV Not Ready | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 12/17/2024 | Approved | JEFFREY MEAD |
| Final | 12/17/2024 | OK to Issue CofO | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 12/17/2024 | SGSOV Approved | JEFFREY MEAD |