740 N ALTA VISTA BLVD 90046
Certificate Information: 740 N ALTA VISTA BLVD 90046
- Application / Permit
- 23047-10000-00981
- Plan Check / Job No.
- B23LA11268
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- eplan: (N) 11' X 26' SWIMMING POOL AND 11' X 7' SPA PER LACITY STANDARD PLAN #268
- Permit Issued
- Issued on 11/8/2023
- Issuing Office
- Current Status
- CofO Issued on 5/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2023 | OMAR GARNICA |
| Corrections Issued | 6/26/2023 | OMAR GARNICA |
| Plan Check Approved | 11/2/2023 | OMAR GARNICA |
| Issued | 11/8/2023 | APPLICANT |
| CofO in Progress | 5/23/2024 | AMIR NAZARIAN |
| Permit Finaled | 5/30/2024 | DEROLD HAUFF |
| CofO Issued | 5/30/2024 | DEROLD HAUFF |
| Permit Finaled | 5/30/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/21/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Mr Carlos Pools And Construction Inc; Lic. No.: 385622-C53 | 978 NORTH AMEILA AVE SAN DIMAS, CA 91773 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pool Piping | 1/5/2024 | Approved | RICHARD DOCKUS |
| Pre-Gunite | 1/5/2024 | Approved | RICHARD DOCKUS |
| Deputy Shotcrete | 1/8/2024 | Conditional Approval | LILIANA PORTILLO |
| Gas Piping or Gas Test | 1/10/2024 | Approved | LILIANA PORTILLO |
| Deck | 2/29/2024 | Approved | AMIR NAZARIAN |
| Enclosure/Fence | 3/15/2024 | Corrections Issued | AMIR NAZARIAN |
| Enclosure/Fence | 3/20/2024 | Corrections Issued | AMIR NAZARIAN |
| Excavation/Setback/Form/Re-Bar | 4/26/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Final | 4/26/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 4/26/2024 | SGSOV Not Ready | AMIR NAZARIAN |
| Pool Equipment Noise Test | 4/30/2024 | Approved | JUAN ESCOTO DELGADO |
| Excavation/Setback/Form/Re-Bar | 5/3/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Final | 5/3/2024 | Corrections Issued | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 5/3/2024 | SGSOV Not Ready | AMIR NAZARIAN |
| Excavation/Setback/Form/Re-Bar | 5/21/2024 | Approved | AMIR NAZARIAN |
| Final | 5/21/2024 | OK to Issue CofO | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 5/21/2024 | SGSOV Approved | AMIR NAZARIAN |