740 N ALTA VISTA BLVD 90046

Certificate Information: 740 N ALTA VISTA BLVD 90046

Application / Permit
23047-10000-00981
Plan Check / Job No.
B23LA11268
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
eplan: (N) 11' X 26' SWIMMING POOL AND 11' X 7' SPA PER LACITY STANDARD PLAN #268
Permit Issued
Issued on 11/8/2023
Issuing Office
Current Status
CofO Issued on 5/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/24/2023 APPLICANT
Assigned to Plan Check Engineer 6/26/2023 OMAR GARNICA
Corrections Issued 6/26/2023 OMAR GARNICA
Plan Check Approved 11/2/2023 OMAR GARNICA
Issued 11/8/2023 APPLICANT
CofO in Progress 5/23/2024 AMIR NAZARIAN
Permit Finaled 5/30/2024 DEROLD HAUFF
CofO Issued 5/30/2024 DEROLD HAUFF
Permit Finaled 5/30/2024 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 10/21/2023 RIDWAN HARDY

Contact Information

Contractor Mr Carlos Pools And Construction Inc; Lic. No.: 385622-C53 978 NORTH AMEILA AVE      SAN DIMAS, CA 91773

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pool Piping 1/5/2024 Approved RICHARD DOCKUS
Pre-Gunite 1/5/2024 Approved RICHARD DOCKUS
Deputy Shotcrete 1/8/2024 Conditional Approval LILIANA PORTILLO
Gas Piping or Gas Test 1/10/2024 Approved LILIANA PORTILLO
Deck 2/29/2024 Approved AMIR NAZARIAN
Enclosure/Fence 3/15/2024 Corrections Issued AMIR NAZARIAN
Enclosure/Fence 3/20/2024 Corrections Issued AMIR NAZARIAN
Excavation/Setback/Form/Re-Bar 4/26/2024 Not Ready for Inspection AMIR NAZARIAN
Final 4/26/2024 Not Ready for Inspection AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 4/26/2024 SGSOV Not Ready AMIR NAZARIAN
Pool Equipment Noise Test 4/30/2024 Approved JUAN ESCOTO DELGADO
Excavation/Setback/Form/Re-Bar 5/3/2024 Not Ready for Inspection AMIR NAZARIAN
Final 5/3/2024 Corrections Issued AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 5/3/2024 SGSOV Not Ready AMIR NAZARIAN
Excavation/Setback/Form/Re-Bar 5/21/2024 Approved AMIR NAZARIAN
Final 5/21/2024 OK to Issue CofO AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 5/21/2024 SGSOV Approved AMIR NAZARIAN