930 N LINDA FLORA DR 90049
Certificate Information: 930 N LINDA FLORA DR 90049
- Application / Permit
- 23047-10000-00945
- Plan Check / Job No.
- B23LA10808
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ePlan NEW 18' X 40' IN GROUND POOL WITH SPA
- Permit Issued
- Issued on 9/20/2023
- Issuing Office
- Current Status
- CofO Issued on 4/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2023 | JAD BASMA |
| Corrections Issued | 6/25/2023 | JAD BASMA |
| Quality Review Completed | 7/5/2023 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 7/13/2023 | JAD BASMA |
| Issued | 9/20/2023 | APPLICANT |
| CofO in Progress | 3/26/2025 | CARLOS MATAMOROS |
| Permit Finaled | 4/4/2025 | RICHARD STEINBACH |
| CofO Issued | 4/4/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/4/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/13/2023 | JAD BASMA |
Contact Information
| Contractor | Casa24 Limited Liability Company; Lic. No.: 1103265-B | , |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/26/2024 | Corrections Issued | CARLOS MATAMOROS |
| Pre-Gunite | 3/26/2024 | Partial Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 5/10/2024 | Corrections Issued | CARLOS MATAMOROS |
| Gas Piping or Gas Test | 7/1/2024 | Approved | CARLOS MATAMOROS |
| Rough-Electrical | 7/1/2024 | Partial Approval | CARLOS MATAMOROS |
| ELECTRICAL-Final | 3/10/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Enclosure/Fence | 3/10/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 3/10/2025 | Approved | CARLOS MATAMOROS |
| Final | 3/10/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Final | 3/10/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Pool/Spa Cover | 3/10/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Pre-Gunite | 3/10/2025 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 3/10/2025 | SGSOV Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 3/18/2025 | Approved | CARLOS MATAMOROS |
| Enclosure/Fence | 3/18/2025 | Approved | CARLOS MATAMOROS |
| Final | 3/18/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Grounding or Bonding | 3/18/2025 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 3/18/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Pool/Spa Cover | 3/18/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Final | 3/24/2025 | Approved | CARLOS MATAMOROS |
| Final | 3/26/2025 | OK to Issue CofO | CARLOS MATAMOROS |