4143 S CLOVERDALE AVE 90008

Certificate Information: 4143 S CLOVERDALE AVE 90008

Application / Permit
23047-10000-00941
Plan Check / Job No.
B23LA10731
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
CONSTRUCT NEW 863 SF SWIMMING POOL WITH SPA 1 OF 2
Permit Issued
Issued on 9/17/2024
Issuing Office
Metro
Current Status
Issued on 9/17/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/9/2023 APPLICANT
Assigned to Plan Check Engineer 6/29/2023 NGHI SU
Corrections Issued 7/5/2023 NGHI SU
Quality Review Completed 7/6/2023 KEN GILL
Building Plans Picked Up 7/18/2023 APPLICANT
Applicant returned to address corrections 8/24/2023 NGHI SU
Plan Check Approved 9/13/2024 NGHI SU
Issued 9/17/2024 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/9/2023 NEIL TUANO
Roof/Waste drainage to street Cleared 8/9/2023 NEIL TUANO
Low Impact Development (LID) Cleared 12/8/2023 SAMUEL LINN
Grading Pre-Inspection Cleared 8/20/2024 NGHI SU

Contact Information

Contractor J J C Construction Inc; Lic. No.: 1075265-B 2307 W 78TH PLACE      INGLEWOOD, CA 90305
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807
Engineer Ho,, Sheng-Zong John; Lic. No.: GE2322 22 LUCERO EAST      IRVINE, CA 92620
Engineer Singer,, Joanne Chapin; Lic. No.: C26900 40530 KINSALE PL      INDIO, CA 92203

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 8/26/2025 Partial Approval LUIS CASTRO
Excavation/Setback/Form/Re-Bar 10/7/2025 Approved LUIS CASTRO
Pre-Gunite 10/7/2025 Approved LUIS CASTRO
Rough-Electrical 10/7/2025 Approved LUIS CASTRO
Rough-Plumbing 10/7/2025 Approved LUIS CASTRO
Deputy Shotcrete 10/15/2025 Conditional Approval DEVON JACKSON
Rough-Electrical 11/4/2025 Partial Approval LUIS CASTRO
Grounding or Bonding 12/10/2025 Approved LUIS CASTRO
Enclosure/Fence 12/31/2025 Corrections Issued BRENDAN MORELLI
Enclosure/Fence 1/6/2026 Corrections Issued LUIS CASTRO
Enclosure/Fence 1/29/2026 Not Ready for Inspection LUIS CASTRO
Enclosure/Fence 1/30/2026 Not Ready for Inspection LUIS CASTRO
Enclosure/Fence 2/3/2026 Partial Approval LUIS CASTRO
Enclosure/Fence 2/5/2026 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 4/13/2026 SGSOV Approved LUIS CASTRO