800 N NIMES ROAD 90077
Certificate Information: 800 N NIMES ROAD 90077
- Application / Permit
- 23047-10000-00798
- Plan Check / Job No.
- B23LA09009
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ePLAN. NEW POOL/SPA BY ENGR'S DESIGN (Grading under 20030-10000-04797)
- Permit Issued
- Issued on 9/21/2023
- Issuing Office
- Current Status
- CofO Issued on 1/29/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2023 | PRANITA SHAH |
| Corrections Issued | 5/30/2023 | PRANITA SHAH |
| Quality Review Completed | 6/9/2023 | GARO TELMI |
| Applicant returned to address corrections | 8/4/2023 | PRANITA SHAH |
| Plan Check Approved | 9/21/2023 | PRANITA SHAH |
| Issued | 9/21/2023 | APPLICANT |
| CofO in Progress | 1/29/2026 | CHRISTOPHER WILSON |
| Permit Finaled | 1/29/2026 | RICHARD STEINBACH |
| CofO Issued | 1/29/2026 | RICHARD STEINBACH |
| Permit Finaled | 1/29/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2023 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 6/9/2023 | ANTHONY MAINEZ |
| ZI | Cleared | 6/12/2023 | MAYELA VILLA |
| GPI Written Notices | Cleared | 9/21/2023 | PRANITA SHAH |
| Grading Pre-Inspection | Cleared | 9/21/2023 | PRANITA SHAH |
Contact Information
| Contractor | M G Partners Inc; Lic. No.: 886387-B | 761 E DAILY DR #140 CAMARILLO, CA 93010 |
| Engineer | Hollingsworth,, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/15/2023 | Partial Approval | CHRISTOPHER WILSON |
| Pre-Inspection | 11/30/2023 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 12/14/2023 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 1/31/2024 | Partial Approval | CHRISTOPHER WILSON |
| Grounding or Bonding | 1/31/2024 | Partial Approval | CHRISTOPHER WILSON |
| Pool Piping | 1/31/2024 | Approved | CHRISTOPHER WILSON |
| Pre-Gunite | 1/31/2024 | Approved | CHRISTOPHER WILSON |
| Rough-Electrical | 1/31/2024 | Partial Approval | CHRISTOPHER WILSON |
| Rough-Plumbing | 1/31/2024 | Partial Approval | CHRISTOPHER WILSON |
| Rough-Plumbing | 3/22/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Rough-Plumbing | 3/26/2024 | Partial Approval | CHRISTOPHER WILSON |
| Pre-Inspection | 7/30/2025 | Partial Inspection | CHRISTOPHER WILSON |
| PLUMBING-Final | 8/14/2025 | Partial Approval | STEPHANIE SWANSON |
| Enclosure/Fence | 8/28/2025 | Corrections Issued | CHRISTOPHER WILSON |
| Special/Order Compliance | 8/28/2025 | Corrections Issued | CHRISTOPHER WILSON |
| Equipment Noise Level | 9/19/2025 | Corrections Issued | CHRISTOPHER WILSON |
| Enclosure/Fence | 9/22/2025 | Approved | CHRISTOPHER WILSON |
| Pre-Inspection | 9/22/2025 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 11/4/2025 | Approved | ANDREW NAVE |
| Final | 11/4/2025 | Corrections Issued | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 11/4/2025 | SGSOV Not Ready | ANDREW NAVE |
| Final | 11/14/2025 | Not Ready for Inspection | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 11/14/2025 | SGSOV Approved | SEAN HAUPT |
| Final | 1/23/2026 | OK to Issue CofO | CHRISTOPHER WILSON |