1231 W ELBERON AVE 90732
Certificate Information: 1231 W ELBERON AVE 90732
- Application / Permit
- 23047-10000-00784
- Plan Check / Job No.
- B23LA08785
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW SWIMMING POOL AND SPA CONSTRUCTION PER LA CITY STANDARD PLAN #265 1 OF 2
- Permit Issued
- Issued on 5/26/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/11/2023 | JOSEPH RAFOLS |
| Corrections Issued | 5/11/2023 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 5/17/2023 | SHANGQIN XIE |
| Issued | 5/26/2023 | APPLICANT |
| CofO in Progress | 10/27/2023 | EUGENE CASSIDY |
| Permit Finaled | 11/1/2023 | ANSON MAGLASANG |
| CofO Issued | 11/1/2023 | ANSON MAGLASANG |
| Permit Finaled | 11/1/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/25/2023 | SERGIO VALENZUELA |
Contact Information
| Contractor | Premier Pools & Spas; Lic. No.: 798298-C53 | 26052 MERIT CIRCLE 106 LAGUNA HILLS, CA 92653 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pool Piping | 6/27/2023 | Approved | JAMES CHAVEZ |
| Pre-Gunite | 6/27/2023 | Approved | JAMES CHAVEZ |
| Special/Order Compliance | 6/27/2023 | Partial Inspection | ANSON MAGLASANG |
| Deck | 7/21/2023 | Approved | ANSON MAGLASANG |
| Grounding or Bonding | 7/21/2023 | Approved | ANSON MAGLASANG |
| Enclosure/Fence | 8/23/2023 | Approved | ANSON MAGLASANG |
| Equipment Noise Level | 9/14/2023 | Approved | JAMES VORHIS |
| Excavation/Setback/Form/Re-Bar | 10/16/2023 | Approved | ANSON MAGLASANG |
| Final | 10/16/2023 | Conditional Approval | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 10/16/2023 | SGSOV Approved | ANSON MAGLASANG |
| Final | 10/27/2023 | OK to Issue CofO | EUGENE CASSIDY |