110 N MAPLETON DR 90077
Certificate Information: 110 N MAPLETON DR 90077
- Application / Permit
- 23047-10000-00748
- Plan Check / Job No.
- B23LA08371
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- EPLAN Pool Remodel with (N) Baja and (N) Spa per standard plan 268 and detail #551. (N) Pool Deck and (N) Railing
- Permit Issued
- Issued on 6/7/2023
- Issuing Office
- Current Status
- Issued on 6/7/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2023 | MINA HABILI |
| Corrections Issued | 5/10/2023 | MINA HABILI |
| Plan Check Approved | 6/6/2023 | MICHAEL LOPEZ |
| Issued | 6/7/2023 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/12/2023 | VASIL MIHALEV |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 10/23/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Pool Piping | 10/23/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Rough-Electrical | 10/23/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Rough-Plumbing | 10/23/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 10/27/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Rough-Electrical | 10/27/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Rough-Plumbing | 10/27/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Enclosure/Fence | 10/30/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 10/30/2023 | Approved | CHRISTOPHER WILSON |
| Grounding or Bonding | 10/30/2023 | Partial Approval | CHRISTOPHER WILSON |
| Pool Piping | 10/30/2023 | Partial Approval | CHRISTOPHER WILSON |
| Pre-Gunite | 10/30/2023 | Approved | CHRISTOPHER WILSON |
| Rough-Electrical | 10/30/2023 | Partial Approval | CHRISTOPHER WILSON |
| Rough-Plumbing | 10/30/2023 | Partial Approval | CHRISTOPHER WILSON |
| Gas Piping or Gas Test | 2/29/2024 | Partial Approval | CHRISTOPHER WILSON |
| Special/Order Compliance | 4/12/2024 | Approved | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 3/26/2026 | SGSOV Not Ready | CHRISTOPHER WILSON |
| Final | 5/8/2026 | Corrections Issued | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 5/8/2026 | SGSOV Not Ready | CARLOS MATAMOROS |