2323 W LOY LANE 90041
Certificate Information: 2323 W LOY LANE 90041
- Application / Permit
- 23047-10000-00594
- Plan Check / Job No.
- B23LA06457
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- eplan: New 17' X 11'-11" swimming pooL AND New 8'-9" x 8'-7" raised (+18") spa. per std plan # 268 and engineer detail #271-60, # 324, #400-60, and # 601-60.
- Permit Issued
- Issued on 6/5/2023
- Issuing Office
- Current Status
- CofO Issued on 12/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2023 | PINANK PATEL |
| Corrections Issued | 4/13/2023 | PINANK PATEL |
| Applicant returned to address corrections | 4/19/2023 | PINANK PATEL |
| Applicant returned to address corrections | 4/27/2023 | PINANK PATEL |
| Applicant returned to address corrections | 5/3/2023 | PINANK PATEL |
| Applicant returned to address corrections | 5/10/2023 | PINANK PATEL |
| Plan Check Approved | 5/18/2023 | LUISANGEL VALENZUELA |
| Issued | 6/5/2023 | APPLICANT |
| CofO in Progress | 12/5/2023 | CRAIG VAUGHAN |
| CofO in Progress | 12/6/2023 | SCOTT FINNILA |
| CofO Issued | 12/7/2023 | DEROLD HAUFF |
| Permit Finaled | 12/7/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/13/2023 | PINANK PATEL |
Contact Information
| Contractor | Huntington Pools Inc; Lic. No.: 985267-C53 | 300 SO WALNUT AVE #401 SAN DIMAS, CA 91773 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 7/17/2023 | Corrections Issued | CRAIG VAUGHAN |
| Rough-Plumbing | 7/17/2023 | Partial Approval | CRAIG VAUGHAN |
| Pre-Gunite | 7/20/2023 | Approved | CRAIG VAUGHAN |
| Rough-Plumbing | 7/20/2023 | Partial Approval | CRAIG VAUGHAN |
| Deputy Shotcrete | 8/1/2023 | Conditional Approval | CRAIG VAUGHAN |
| Deck | 10/11/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Enclosure/Fence | 10/16/2023 | Approved | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 10/30/2023 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 10/30/2023 | SGSOV Not Ready | CRAIG VAUGHAN |
| Equipment Noise Level | 11/7/2023 | Partial Inspection | ANDEY CHAPARRO |
| Final | 12/4/2023 | OK to Issue CofO | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 12/4/2023 | SGSOV Approved | CRAIG VAUGHAN |