3919 W BOYCE AVE 90039
Certificate Information: 3919 W BOYCE AVE 90039
- Application / Permit
- 23047-10000-00577
- Plan Check / Job No.
- B23LA06094
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW POOL AND SPA per Standard PLAN #270
- Permit Issued
- Issued on 6/13/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2023 | LUKE GONZALES |
| Corrections Issued | 4/4/2023 | LUKE GONZALES |
| Plan Check Approved | 6/9/2023 | MINA HABILI |
| Plan Check Approved | 6/13/2023 | MINA HABILI |
| Issued | 6/13/2023 | APPLICANT |
| CofO in Progress | 2/8/2024 | ALIZAH MAYAGOITIA |
| CofO Issued | 2/12/2024 | DEROLD HAUFF |
| Permit Finaled | 2/12/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Legacy Builders & Remodeling Inc; Lic. No.: 1046784-B | 9507 DORK ST PICO RIVERA, CA 90660 |
| Engineer | Cristescu,, Barbu Dan; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/27/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Rough-Plumbing | 6/27/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 7/24/2023 | Approved | HAMIK HARTOUNIAN |
| Pool Piping | 7/24/2023 | Approved | HAMIK HARTOUNIAN |
| Deputy Shotcrete | 8/8/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Final | 8/15/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 8/15/2023 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Enclosure/Fence | 11/30/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Enclosure/Fence | 12/5/2023 | Approved | HAMIK HARTOUNIAN |
| Equipment Noise Level | 12/5/2023 | Approved | JUAN ESCOTO DELGADO |
| Final | 2/1/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 2/1/2024 | SGSOV Approved | HAMIK HARTOUNIAN |
| Final | 2/6/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| Final | 2/8/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |