707 N LARK CT 90065
Certificate Information: 707 N LARK CT 90065
- Application / Permit
- 23047-10000-00564
- Plan Check / Job No.
- B23LA05937
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 23'-7" X 14'-0" POOL AND SPA - PER STANDARD PLAN 268 AND SUPPLEMENTARY ENGINEERED DETAIL
- Permit Issued
- Issued on 7/14/2023
- Issuing Office
- Current Status
- CofO Issued on 1/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 4/10/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 5/17/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 6/14/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 6/22/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 6/22/2023 | DANIEL ABRAMYAN |
| No Progress | 6/22/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 6/30/2023 | DANIEL ABRAMYAN |
| Issued | 7/14/2023 | APPLICANT |
| CofO in Progress | 1/18/2024 | ALIZAH MAYAGOITIA |
| No Progress | 1/21/2024 | DEROLD HAUFF |
| CofO in Progress | 1/26/2024 | SCOTT FINNILA |
| Permit Finaled | 1/28/2024 | DEROLD HAUFF |
| CofO Issued | 1/28/2024 | DEROLD HAUFF |
| Permit Finaled | 1/28/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/9/2023 | DANIEL ABRAMYAN |
| Specific Plan | Cleared | 5/9/2023 | PABLO ESTRADA |
Contact Information
| Contractor | Aqua Pool & Spa Construction Inc; Lic. No.: 1046115-C53 | 7361 ETHEL AVE #4 NORTH HOLLYWOOD, CA 91605 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 8/25/2023 | Approved | HAMIK HARTOUNIAN |
| Pre-Gunite | 8/25/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Pre-Gunite | 8/30/2023 | Approved | OSVALDO PARAMO |
| Deputy Shotcrete | 9/1/2023 | Conditional Approval | OSVALDO PARAMO |
| Deck | 9/27/2023 | Partial Approval | OSVALDO PARAMO |
| Grounding or Bonding | 11/3/2023 | Approved | ALIZAH MAYAGOITIA |
| Enclosure/Fence | 11/20/2023 | Approved | OSVALDO PARAMO |
| Pool Equipment Noise Test | 12/7/2023 | Not Ready for Inspection | JUAN ESCOTO DELGADO |
| SGSOV-Seismic Gas S/O Valve | 12/11/2023 | SGSOV Not Ready | OSVALDO PARAMO |
| Equipment Noise Level | 1/4/2024 | Partial Inspection | ANDEY CHAPARRO |
| Excavation/Setback/Form/Re-Bar | 1/4/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 1/4/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Pool Equipment Noise Test | 1/4/2024 | Approved | ANDEY CHAPARRO |
| SGSOV-Seismic Gas S/O Valve | 1/4/2024 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Final | 1/12/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 1/12/2024 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Final | 1/17/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |