4853 E FARQUHAR ST 90032
Certificate Information: 4853 E FARQUHAR ST 90032
- Application / Permit
- 23047-10000-00493
- Plan Check / Job No.
- B23LA05465
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- Fiberglass pool installation per ESR 298
- Permit Issued
- Issued on 12/9/2024
- Issuing Office
- Current Status
- Issued on 12/9/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2023 | JOE VO |
| Corrections Issued | 4/14/2023 | JOE VO |
| Quality Review Completed | 4/17/2023 | GARO TELMI |
| Applicant returned to address corrections | 8/3/2023 | JOE VO |
| Plan Check Approved | 1/4/2024 | JOE VO |
| Issued | 12/9/2024 | APPLICANT |
Permit Application Clearance Information
| "D" conditions | Cleared | 1/3/2024 | DAVID URITA |
| "Q" conditions | Cleared | 1/3/2024 | DAVID URITA |
Contact Information
| Contractor | V I P Construction; Lic. No.: 664861-C53 | 23052 ALICIA PKWY #H500 MISSION VIEJO, CA 92692 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pool Piping | 6/17/2025 | Corrections Issued | LILIANA PORTILLO |
| Pool Piping | 6/30/2025 | Partial Approval | LILIANA PORTILLO |
| Deck | 7/11/2025 | Approved | LILIANA PORTILLO |
| Enclosure/Fence | 8/20/2025 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 8/20/2025 | SGSOV Not Ready | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 5/5/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 5/5/2026 | Corrections Issued | LILIANA PORTILLO |
| Pre-Gunite | 5/5/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 5/5/2026 | SGSOV Not Ready | LILIANA PORTILLO |