2811 S OAKHURST AVE 90034
Certificate Information: 2811 S OAKHURST AVE 90034
- Application / Permit
- 23047-10000-00441
- Plan Check / Job No.
- B23LA04217
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- PROPOSED SWIMMING POOL AND SPA
- Permit Issued
- Issued on 6/23/2023
- Issuing Office
- Current Status
- CofO Issued on 8/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2023 | CRYSTEL MAALOUF |
| Corrections Issued | 3/20/2023 | CRYSTEL MAALOUF |
| Quality Review Completed | 4/7/2023 | FARUK SEZER |
| Applicant returned to address corrections | 6/5/2023 | CRYSTEL MAALOUF |
| Plan Check Approved | 6/23/2023 | CRYSTEL MAALOUF |
| Issued | 6/23/2023 | APPLICANT |
| CofO in Progress | 8/9/2024 | KIRK SANDERS |
| Permit Finaled | 8/27/2024 | RICHARD STEINBACH |
| CofO Issued | 8/27/2024 | RICHARD STEINBACH |
| Permit Finaled | 8/27/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Construction within easement | Cleared | 6/10/2023 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 6/23/2023 | CRYSTEL MAALOUF |
Contact Information
| Architect | Ribeiro, De Moura, Ricardo Jorge; Lic. No.: C38075 | 5236 YARMOUTH AVE #113 ENCINO, CA 91316 |
| Contractor | Owner-Builder | , |
| Engineer | Cristescu,, Barbu Dan; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
| Engineer | Ostowari,, Sohrab; Lic. No.: C41014 | 7012 HELMSDALE RD WEST HILLS, CA 91307 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 7/21/2023 | Corrections Issued | CLAYTON GRAHAM |
| Pre-Gunite | 7/31/2023 | Corrections Issued | CLAYTON GRAHAM |
| Pre-Gunite | 10/17/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Pre-Gunite | 11/3/2023 | Approved | CLAYTON GRAHAM |
| Gas Piping or Gas Test | 12/13/2023 | Approved | OGANES TARAKHCHYAN |
| Rough-Electrical | 12/13/2023 | Approved | OGANES TARAKHCHYAN |
| Grounding or Bonding | 2/28/2024 | Partial Approval | MEL KHACHATOURIAN |
| Enclosure/Fence | 5/10/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Enclosure/Fence | 5/22/2024 | Approved | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 6/26/2024 | Approved | SEAN HAUPT |
| Final | 6/26/2024 | Corrections Issued | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 6/26/2024 | SGSOV Approved | SEAN HAUPT |
| Equipment Noise Level | 8/6/2024 | Approved | ANDEY CHAPARRO |
| Final | 8/8/2024 | OK to Issue CofO | KIRK SANDERS |