1360 N LAUREL WAY 90210
Certificate Information: 1360 N LAUREL WAY 90210
- Application / Permit
- 23047-10000-00288
- Plan Check / Job No.
- B23LA01335
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ePlan: SWIMMING POOL AND SPA
- Permit Issued
- Issued on 6/27/2023
- Issuing Office
- Current Status
- CofO Issued on 6/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2023 | DANIEL YIP |
| Corrections Issued | 2/22/2023 | DANIEL YIP |
| Quality Review Completed | 2/23/2023 | GARO TELMI |
| Applicant returned to address corrections | 4/21/2023 | DANIEL YIP |
| Plan Check Approved | 5/25/2023 | DANIEL YIP |
| No Progress | 6/27/2023 | DANIEL YIP |
| Plan Check Approved | 6/27/2023 | DANIEL YIP |
| Issued | 6/27/2023 | APPLICANT |
| CofO in Progress | 5/21/2026 | CARLOS MATAMOROS |
| Permit Finaled | 6/2/2026 | RICHARD STEINBACH |
| CofO Issued | 6/2/2026 | RICHARD STEINBACH |
| Permit Finaled | 6/2/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Tallen & Tyce Development Inc; Lic. No.: 1029383-B | , |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/23/2023 | Partial Approval | BRENDAN LOONEY |
| Deputy Other (see comments) | 10/4/2023 | Approved | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 10/4/2023 | Partial Approval | BRENDAN LOONEY |
| Deputy Other (see comments) | 10/5/2023 | Conditional Approval | MICHAEL PELHAM |
| Pool Piping | 11/2/2023 | Corrections Issued | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 11/3/2023 | Partial Approval | BRENDAN LOONEY |
| Deputy Shotcrete | 11/6/2023 | Conditional Approval | BRENDAN LOONEY |
| Deputy Shotcrete | 11/6/2023 | Conditional Approval | MICHAEL PELHAM |
| Rough-Plumbing | 11/29/2023 | Partial Approval | BRENDAN LOONEY |
| Grounding or Bonding | 2/27/2024 | Not Ready for Inspection | SEAN HAUPT |
| Pool Piping | 2/27/2024 | Not Ready for Inspection | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 3/11/2024 | Not Ready for Inspection | SEAN HAUPT |
| Deputy Other (see comments) | 3/14/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Shotcrete | 3/15/2024 | Conditional Approval | MICHAEL PELHAM |
| Enclosure/Fence | 3/10/2026 | Corrections Issued | CARLOS MATAMOROS |
| Enclosure/Fence | 3/12/2026 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 4/17/2026 | Approved | CARLOS MATAMOROS |
| Final | 4/17/2026 | Not Ready for Inspection | CARLOS MATAMOROS |
| Pre-Gunite | 4/17/2026 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 4/17/2026 | SGSOV Not Ready | CARLOS MATAMOROS |
| ELECTRICAL-Final | 5/21/2026 | Approved | CARLOS MATAMOROS |
| Final | 5/21/2026 | OK to Issue CofO | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 5/21/2026 | SGSOV Approved | CARLOS MATAMOROS |