161 S CITRUS AVE 90036
Certificate Information: 161 S CITRUS AVE 90036
- Application / Permit
- 23047-10000-00258
- Plan Check / Job No.
- B23VN02019
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- REMODEL (E) POOL TO DECREASE LENGTH TO 22'-0" x 14'-0" POOL, REMOVE (E) ATTACHED SPA, ADD (N) 7'-0" x 10'-0" SPA AND (N) BAJA WITHIN SHELL, AND ADD (N) POOL COVER VAULT PER CITY STD. PLAN #268 AND ENGINEERING DETAILS.
- Permit Issued
- Issued on 2/24/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2023 | ALFRED RAMIREZ |
| Corrections Issued | 2/17/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 2/24/2023 | ISIS ARGUETA |
| Issued | 2/24/2023 | APPLICANT |
| CofO in Progress | 5/4/2026 | RAUL BARAJAS |
| Permit Finaled | 5/5/2026 | DEROLD HAUFF |
| CofO Issued | 5/5/2026 | DEROLD HAUFF |
| Permit Finaled | 5/5/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/21/2023 | TORI CHEN |
Contact Information
| Contractor | National Pools Inc; Lic. No.: 963509-C53 | 15439 MONTE ST SYLMAR, CA 91342 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/8/2023 | Conditional Approval | RICHARD DOCKUS |
| Pre-Gunite | 3/13/2023 | Approved | RICHARD DOCKUS |
| Deputy Shotcrete | 3/17/2023 | Conditional Approval | RICHARD DOCKUS |
| Enclosure/Fence | 7/13/2023 | Corrections Issued | JOSEPH MCGARRY |
| Deck | 7/17/2023 | Approved | JOSEPH MCGARRY |
| Enclosure/Fence | 7/17/2023 | Approved | JOSEPH MCGARRY |
| Equipment Noise Level | 7/20/2023 | Approved | ZEYDI STEWART |
| Final | 8/28/2023 | Corrections Issued | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 8/28/2023 | SGSOV Approved | ROY SPAULDING |
| Final | 3/31/2026 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 4/6/2026 | Corrections Issued | RONNIE MINDANAO |
| Final | 4/27/2026 | Conditional Approval | RONNIE MINDANAO |
| Final | 5/4/2026 | OK to Issue CofO | RAUL BARAJAS |