3000 S CASTLE HEIGHTS AVE 90034
Certificate Information: 3000 S CASTLE HEIGHTS AVE 90034
- Application / Permit
- 23047-10000-00237
- Plan Check / Job No.
- B23LA02521
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) POOL PER LA CITY STANDARD PLAN #268
- Permit Issued
- Issued on 3/13/2023
- Issuing Office
- Current Status
- CofO Issued on 9/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2023 | GEORGE ALVAREZ |
| Corrections Issued | 2/14/2023 | GEORGE ALVAREZ |
| Plan Check Approved | 3/13/2023 | LUKE GONZALES |
| Issued | 3/13/2023 | APPLICANT |
| Permit Finaled | 9/16/2024 | RICHARD STEINBACH |
| CofO Issued | 9/16/2024 | RICHARD STEINBACH |
| Permit Finaled | 9/16/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/13/2023 | LUKE GONZALES |
| ZA Case | Cleared | 3/13/2023 | JASON CHAN |
Contact Information
| Contractor | A Sarian Pools; Lic. No.: 901693-C53 | P O BOX 903 MONTEBELLO, CA 90640 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 4/6/2023 | Corrections Issued | MICHAEL PELHAM |
| Pre-Gunite | 5/22/2023 | Corrections Issued | JOHNNY MIRANDA |
| Pre-Gunite | 6/5/2023 | Approved | JEREMY TODD |
| Deputy Shotcrete | 6/15/2023 | Conditional Approval | DAVID FEILER |
| Grounding or Bonding | 12/13/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Enclosure/Fence | 5/28/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Enclosure/Fence | 6/13/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Enclosure/Fence | 6/27/2024 | Approved | SEAN HAUPT |
| Equipment Noise Level | 8/6/2024 | Approved | ANDEY CHAPARRO |
| Excavation/Setback/Form/Re-Bar | 8/26/2024 | Approved | ASHLEY THOMPSON |
| Final | 8/26/2024 | Corrections Issued | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 8/26/2024 | SGSOV Approved | ASHLEY THOMPSON |
| Special/Order Compliance | 8/26/2024 | Partial Inspection | REGINA MENDEZ |
| Final | 9/6/2024 | Corrections Issued | KIRK SANDERS |
| Final | 9/11/2024 | Conditional Approval | ASHLEY THOMPSON |