2044 N STRADELLA ROAD 90077

Certificate Information: 2044 N STRADELLA ROAD 90077

Application / Permit
23047-10000-00182
Plan Check / Job No.
B22LA25877
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
eplan. new swimming pool
Permit Issued
Issued on 9/5/2023
Issuing Office
Current Status
Issued on 9/5/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/22/2022 APPLICANT
Assigned to Plan Check Engineer 1/26/2023 CRYSTEL MAALOUF
Corrections Issued 2/3/2023 CRYSTEL MAALOUF
Quality Review Completed 2/24/2023 FARUK SEZER
Applicant returned to address corrections 6/7/2023 CRYSTEL MAALOUF
Applicant returned to address corrections 7/19/2023 CRYSTEL MAALOUF
Applicant returned to address corrections 8/21/2023 CRYSTEL MAALOUF
Plan Check Approved 9/1/2023 CRYSTEL MAALOUF
Issued 9/5/2023 APPLICANT

Permit Application Clearance Information

GPI Written Notices Cleared 8/31/2023 CRYSTEL MAALOUF
Grading Pre-Inspection Cleared 8/31/2023 CRYSTEL MAALOUF

Contact Information

Architect Jazayeri,, Siavash; Lic. No.: C22240 20230 WELLS DR      WOODLAND HILLS, CA 91364
Contractor Lux Builders Group Inc; Lic. No.: 1050761-B       ,
Engineer Pirbadian,, Amir; Lic. No.: C72413 17514 VENTURA BLVD.   SUITE 206    ENCINO, CA 91346

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Other (see comments) 11/2/2023 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 11/2/2023 Partial Approval CHRISTOPHER WILSON
Deputy Pre-Stress Concrete 11/3/2023 Conditional Approval MICHAEL PELHAM
Deputy Other (see comments) 11/6/2023 Conditional Approval MICHAEL PELHAM
Deputy Other (see comments) 11/13/2023 Conditional Approval MICHAEL PELHAM
Deputy Other (see comments) 12/8/2023 Conditional Approval MICHAEL PELHAM
Deputy Shotcrete 4/10/2024 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 4/11/2024 Partial Approval MICHAEL PELHAM
Deputy Shotcrete 5/1/2024 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 5/6/2024 Corrections Issued CHRISTOPHER WILSON
Grounding or Bonding 5/6/2024 Not Ready for Inspection CHRISTOPHER WILSON
Pool Piping 5/6/2024 Not Ready for Inspection CHRISTOPHER WILSON
Pre-Gunite 5/6/2024 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Other (see comments) 5/7/2024 Approved MICHAEL PELHAM
Pre-Gunite 5/7/2024 Approved MICHAEL PELHAM
Deputy Shotcrete 5/21/2024 Conditional Approval CHRISTOPHER WILSON
Gunite 2/6/2025 Partial Inspection CHRISTOPHER WILSON
ELECTRICAL-Final 4/14/2026 Not Ready for Inspection CHRISTOPHER WILSON
Gas Piping or Gas Test 4/14/2026 Approved CHRISTOPHER WILSON
Gunite 4/14/2026 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Final 4/14/2026 Not Ready for Inspection CHRISTOPHER WILSON
Special/Order Compliance 4/14/2026 Not Ready for Inspection CHRISTOPHER WILSON