4601 N GREENBUSH AVE 91423
Certificate Information: 4601 N GREENBUSH AVE 91423
- Application / Permit
- 23047-10000-00135
- Plan Check / Job No.
- B23LA01162
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 31' X 18' POOL AND 8'-6" X 6' SPA - PER LA CITY STANDARD PLAN #268
- Permit Issued
- Issued on 5/17/2023
- Issuing Office
- Current Status
- CofO Issued on 7/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2023 | ISIS ARGUETA |
| Corrections Issued | 1/30/2023 | ISIS ARGUETA |
| Applicant returned to address corrections | 5/10/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 5/12/2023 | DANIEL ABRAMYAN |
| Issued | 5/17/2023 | APPLICANT |
| CofO in Progress | 7/19/2023 | MISAEL ESPARZA |
| Permit Finaled | 7/19/2023 | MICHAEL SMITH |
| CofO Issued | 7/19/2023 | MICHAEL SMITH |
| Permit Finaled | 7/19/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 5/8/2023 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/22/2023 | Corrections Issued | JACK KARGODORIAN |
| Pre-Gunite | 5/22/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Rough-Electrical | 5/22/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Rough-Plumbing | 5/22/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 5/26/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Pre-Gunite | 5/26/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Rough-Electrical | 5/26/2023 | Approved | JOHN COLEMAN |
| Rough-Plumbing | 5/26/2023 | Approved | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 6/2/2023 | Approved | JOHN COLEMAN |
| Deputy Shotcrete | 6/15/2023 | Conditional Approval | JUAN VALENZUELA |
| Grounding or Bonding | 6/20/2023 | Approved | JOHN COLEMAN |
| Final | 7/14/2023 | Corrections Issued | JACK KARGODORIAN |
| Pool Equipment Noise Test | 7/14/2023 | Approved | FELIPE PENICHE |
| SGSOV-Seismic Gas S/O Valve | 7/14/2023 | SGSOV Approved | JACK KARGODORIAN |
| Final | 7/18/2023 | OK to Issue CofO | MISAEL ESPARZA |